Difference between revisions of "Controls To Do List"
From GlueXWiki
m |
m |
||
Line 6: | Line 6: | ||
*** Should we locate the main PLC in the hall? | *** Should we locate the main PLC in the hall? | ||
** '''''Resolution''''' | ** '''''Resolution''''' | ||
− | *** Bryan and Brent say the high-class switches we will use in the hall are extremely reliable, as reliable as the PLC itself. | + | *** Bryan and Brent say the high-class switches we will use in the hall are extremely reliable, as reliable as the PLC itself, so there doesn't seem to be a good reason to use ControlNet. |
+ | ** '''''To Do''''' | ||
+ | *** Test what happens if an Ethernet cable is unplugged. | ||
Revision as of 12:06, 3 June 2011
- Should we use ControlNet as well as Ethernet/IP in the hall?
- Notes
- Is there really a network reliability problem?
- Would we have to run a copper line to the counting house?
- Should we use an additional PLC in the hall?
- Should we locate the main PLC in the hall?
- Resolution
- Bryan and Brent say the high-class switches we will use in the hall are extremely reliable, as reliable as the PLC itself, so there doesn't seem to be a good reason to use ControlNet.
- To Do
- Test what happens if an Ethernet cable is unplugged.
- Notes
- When should we use a PC104 vs an IOC on a PC vs direct PLC control?
- Notes
- Should the FDC gas system use just PLC control and not use a PC104?
- Notes