Difference between revisions of "Controls To Do List"
From GlueXWiki
m |
m |
||
Line 1: | Line 1: | ||
* Should we use ControlNet as well as Ethernet/IP? | * Should we use ControlNet as well as Ethernet/IP? | ||
− | ** Is there really a network reliability problem? | + | ** '''Notes:''' |
− | ** Would we have to run a copper line to the counting house? | + | *** Is there really a network reliability problem? |
− | ** Should we use an additional PLC in the hall? | + | *** Would we have to run a copper line to the counting house? |
− | ** Should we locate the main PLC in the hall? | + | *** Should we use an additional PLC in the hall? |
− | ** '''Resolved | + | *** Should we locate the main PLC in the hall? |
+ | ** '''Resolved''' | ||
+ | *** Bryan and Brent say the high-class switches we will use in the hall are extremely reliable, as reliable as the PLC itself. | ||
* When should we use a PC104 vs an IOC on a PC vs direct PLC control? | * When should we use a PC104 vs an IOC on a PC vs direct PLC control? | ||
** Should the FDC gas system use just PLC control and not use a PC104? | ** Should the FDC gas system use just PLC control and not use a PC104? |
Revision as of 11:58, 3 June 2011
- Should we use ControlNet as well as Ethernet/IP?
- Notes:
- Is there really a network reliability problem?
- Would we have to run a copper line to the counting house?
- Should we use an additional PLC in the hall?
- Should we locate the main PLC in the hall?
- Resolved
- Bryan and Brent say the high-class switches we will use in the hall are extremely reliable, as reliable as the PLC itself.
- Notes:
- When should we use a PC104 vs an IOC on a PC vs direct PLC control?
- Should the FDC gas system use just PLC control and not use a PC104?