Difference between revisions of "Run Coordination Meetings:Spring2025"

From GlueXWiki
Jump to: navigation, search
(General Information)
(General Information)
Line 104: Line 104:
 
*** Jan. ?? - 24, ?? days (beam restoration): Alexandre Deur  
 
*** Jan. ?? - 24, ?? days (beam restoration): Alexandre Deur  
 
*** Jan. 24 - 29, 6 days: Alexandre Deur  
 
*** Jan. 24 - 29, 6 days: Alexandre Deur  
*** Jan. 29 - Feb. 5, 1 week:  
+
*** Jan. 29 - Feb. 5, 1 week: Igal Jaegle
 
*** Feb. 5-12, 1 week:  Simon Taylor
 
*** Feb. 5-12, 1 week:  Simon Taylor
 
*** Feb. 12-19, 1 week: Edmundo Barriga
 
*** Feb. 12-19, 1 week: Edmundo Barriga

Revision as of 09:02, 16 October 2024

Spring 2025 Run

Google Spreadsheet. 


GlueX experiment (January 24 - July 20 2025)


Connect Information

To connect from the outside by phone please do the following

1.) To join via ZoomGov: connect Meeting ID: 1613772645 / Passcode 8394

2.) To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 660743227.

3.) To join via phone, use one of the following numbers and the Conference ID: 660743227.

4.) The moderator code is 8394

Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

Specific instructions for connecting from JLab's Hall D conference room:

  • Turn polycon on if necessary (do it before turning the computer on)
  • With the polycon, place a call at 199.48.152.152
  • Press # to enable the polycom keypad, then enter the meeting id: 660743227 and #
  • You may have to unmute the microphone: #*4
  • Turn the computer on if needed

Meeting General Agenda

Run planning meetings:


Beam and Hall configuration

  • Commission upgraded ECal.
  • FCAL commissioning
  • Experiment: GlueX-II/JEF.
  • Beam energy expected:
    • TBD GeV
  • Solenoid:
    • 1350A
  • CW Beam:
    • 250 MHz frequency.
    • Range: TBD nA.
    • Chopper slit: TBD
    • Standard current and radiators
      • ~TBD nA on a 4.1·10-4 R.L. radiator (50 μm diamond). (RSAD limit 400nA on 58 μm diamond))
      • ~TBD on a 33.7·10-5 R.L. AL radiator (30 µm Al). (RSAD limit 480nA on 30 µm Al radiator))
  • Position Slow Lock on or FFB on (FFB doesn't operate below 50nA).
  • Radiators:
    • Goniometer radiators: To be updated
      • Diamond JD70-103 (50 μm - 4.1·10-4 R.L., 7×7 mm²) Used in CPP. We will start with this diamond
      • Diamond JD70-107 (55 μm - 4.6·10-4 R.L., 7×7 mm²) - To be used once JD70-103 becomes deficient. New crystal. (Not expected to be great according to rocking curve.)
      • (Diamond JD70-109 (50 μm - 4.1·10-4 R.L., 7×7 mm²) - New crystal - Not expected to be good according to rocking curve.)
      • (Diamond JD70-105 (47 μm - 3.9·10-4 R.L., 7×7 mm²) - Spent: used for the second part of GlueX's Fall 2018 run and Fall 2019/Spring 2020/Fall 2021)
      • (Diamond JD70-106 (50 μm - 4.1·10-4 R.L., 7×7 mm²) - Aligned and used shortly during Tagger Accidental test in Spring 2020. Did not display sharp coherent peak.)
      • Amorphous 40 μm Al radiator (44.9·10-5 R.L.)
      • Amorphous 1.86·10-5 R.L., (for TAC run).
    • Amorphous
      • 1.64 µm Al (1.86·10-5 R.L., see study)
      • 10 µm Al (11.2·10-5 R.L.)
      • 30 µm Al (33.7·10-5 R.L.)
  • Tagger quadrupole on (-4.2 A).
  • Collimator hole: Default running: 5.0 mm.
  • PS converter: 75 μm To be confirmed
  • Miscellaneous:
    • PS test area (tests will be performed in parallel with GlueX data taking):

General Information

This document describes the run plan for the Hall D Spring 2025 run.

  1. January TBD: Electron beam restoration.
  2. January 24th - July 20th: 26 weeks for upgraded ECal commissioning and GlueX-II/JEF.
  • Accelerator overall plan and priorities: Deliver physics beam to 4 halls
    • Anything special for other hall runs?
  • Expected Staffing and responsibilities:
    • The Run Coordinator oversees the run:
      • Jan. ?? - 24, ?? days (beam restoration): Alexandre Deur
      • Jan. 24 - 29, 6 days: Alexandre Deur
      • Jan. 29 - Feb. 5, 1 week: Igal Jaegle
      • Feb. 5-12, 1 week: Simon Taylor
      • Feb. 12-19, 1 week: Edmundo Barriga
      • Feb. 19-26, 1 week: Colin Gleason
      • Feb. 26-March 5, 1 week: Igal Jaegle
      • March 5-12, 1 week: Simon Taylor
      • March 12-19, 1 week: Mike McCaughan
      • March 19-26, 1 week: Drew Smith
      • March 26-Apr. 2, 1 week: Naomi Jarvis
      • Apr. 2-9, 1 week: Boris Grube
      • Apr. 9-16, 1 week: Mark Dalton
      • Apr. 16-23, 1 week: Hao Li
      • Apr. 23-30, 1 week: Mike McCaughan
      • Apr. 20-May 7, 1 week: Alexandre Deur
      • May 7-14, 1 week: Richard Jones
      • May 14-21, 1 week: Justin Stevens
      • May 21-28, 1 week: Boris Grube
      • May 28-June 4, 1 week: Amy Schertz
      • June 4-11, 1 week: Naomi Jarvis
      • June 11-18, 1 week: Edmundo Barriga
      • June 18-25, 1 week: Drew Smith
      • June 25-July 2, 1 week: Hao Li
      • July 2-9, 1 week: Susan Schandmand
      • July 9-16, 1 week: Susan Schandmand
      • July 16-20, 4 days: Mark Dalton
    • The Physics Division Liaison (PDL) and Hall D Work Coordinator/Safety Warden (S. Spiegel) verify that the proper safety rules are followed. PDL is:
      • PDL: B.Zihlmann
    • The analysis coordinator (Alexander Austregesilo) oversees the off-line diagnostic of the different systems and analysis of the data.
    • Shifts: 2 person shifts: 1 local leader and 1 worker scheduled through the GlueX shift scheduler.
  • Coordination Activities:
    • The RC will attend the MCC meetings at 7:45am and 8:00am and the weekly MCC meeting (Wednesday, 1:30pm). The PDL will attend the weekly MCC meeting.
    • Run meetings: broadcasted on Zoom. 8:45am in the counting house conference room. The Run Coordinator will be responsible for organizing and chairing the meeting.

Runplan

Hall D situation room (current run plan)

Hall D counting room white board


Accelerator status

Hot Checkout

To be completed by TBD

0% ready ; 0% checked ; 100% not ready

Readiness for Spring 2025 run

Live Camera Feeds from the Four Counting Houses

  1. These feeds SHOULD be open and visible at all times from one of the monitors in each of the counting houses. (currently this is not working; we should post instructions how to establish this connection. J.R.)
  2. Management cautions AGAINST opening them from other locations or offsite, out of concern for available bandwidth.

Running Shifts Remote