Difference between revisions of "JEF meeting, September 6, 2024"
From GlueXWiki
(→Agenda) |
|||
Line 22: | Line 22: | ||
* - Expect one student from Wuhan, waiting for the US visa | * - Expect one student from Wuhan, waiting for the US visa | ||
''' [https://halldweb.jlab.org/wiki/index.php/ECAL_Commissioning ECAL commissioning]''' -- Sasha, All | ''' [https://halldweb.jlab.org/wiki/index.php/ECAL_Commissioning ECAL commissioning]''' -- Sasha, All | ||
+ | |||
'''Beam tests with the PS''' | '''Beam tests with the PS''' | ||
* measure shower beam profile and reconstruction in the crystal/LG transition region | * measure shower beam profile and reconstruction in the crystal/LG transition region |
Revision as of 08:51, 6 September 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
- - HV long cable: Sammy and Mindy are finishing up with assembling cables, 2 cables are left
- - HV distribution boards [1][2]
- - 5 (12 x 4) and 5 (6 x 8) boards have been received. Chris checked connections. All remaining PCB boards are expected to be in the lab on Sep 12.
- - Chris is finalizing design of the distribution boxes (each box will comprise 9 PCBs). He expects to submit PR during next week.
- - Fix front panel of two LV distribution boards [3]
- - new plates for the LV distribution boards should arrive to JLab during next week. Need to re-install 2 distribution boards and connect cables
- - LED: Started testing the prototype of the LMS (need to make the detector room light tight)
Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Installation and testing dividers has been completed [4]
- - need to arrange cables on chains
- - need to arrange cables on cable trays
Students -- Sasha
- - Expect one student from Wuhan, waiting for the US visa
ECAL commissioning -- Sasha, All
Beam tests with the PS
- measure shower beam profile and reconstruction in the crystal/LG transition region
- (install prototype with 5x5 PbWO4 modules + ? LG)
Other hardware projects
- prototype of the ECAL veto counter (?)
Analysis/Simulation