*'''Preparation of parts for ECAL''' -- Sasha | *'''Preparation of parts for ECAL''' -- Sasha | ||
− | ** - HV long cable: Sammy and Mindy | + | ** - HV long cable: Sammy and Mindy are finishing up with assembling 10 cables |
** - HV distribution boards [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg] | ** - HV distribution boards [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg] | ||
** - Fix front panel of two LV distribution boards, re-install the boards on the detector frame [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/lv_board1.jpg] | ** - Fix front panel of two LV distribution boards, re-install the boards on the detector frame [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/lv_board1.jpg] |
Revision as of 08:14, 6 September 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- - two remaining bundle of cables will be ready in about a week
- Installation and testing cables and dividers [7]
- Installation of long signal cables [8]
- Installation LV patch panels and cables [9]
- Installation of optical fibers [10]
- Detector installation page
- Safety briefings
- Students -- Sasha
- - Expect one student from Wuhan, waiting for the US visa
- Beam tests with the PS
- measure shower beam profile and reconstruction in the crystal/LG transition region
- (install prototype with 5x5 PbWO4 modules + ? LG)
- Other hardware projects
- prototype of the ECAL veto counter (?)