Difference between revisions of "JEF meeting, August 16, 2024"
From GlueXWiki
(→Agenda) |
|||
Line 22: | Line 22: | ||
** [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/Document_240716_195013-1.pdf Safety briefings] | ** [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/Document_240716_195013-1.pdf Safety briefings] | ||
* '''Students''' -- Sasha | * '''Students''' -- Sasha | ||
− | ** - Expect one student from Wuhan, | + | ** - Expect one student from Wuhan, waiting for the US visa |
* '''Beam tests with the PS''' | * '''Beam tests with the PS''' | ||
*** measure shower beam profile and reconstruction in the crystal/LG transition region | *** measure shower beam profile and reconstruction in the crystal/LG transition region |
Revision as of 09:33, 16 August 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- - two remaining bundle of cables will be ready in about a week
- Installation and testing cables and dividers [7]
- Installation of long signal cables [8]
- Installation LV patch panels and cables [9]
- Installation of optical fibers [10]
- Detector installation page
- Safety briefings
- Students -- Sasha
- - Expect one student from Wuhan, waiting for the US visa
- Beam tests with the PS
- measure shower beam profile and reconstruction in the crystal/LG transition region
- (install prototype with 5x5 PbWO4 modules + ? LG)
- Other hardware projects
- prototype of the ECAL veto counter (?)
- Analysis/Simulation
- Close shower separation studies -- Laveen
- New manpower for the upcoming run and data analysis, -- Liping