Difference between revisions of "JEF meeting, July 26, 2024"
From GlueXWiki
(Created page with "Meeting time and location: *9:30 am EST (JLab time) remote only * [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection inform...") |
(→Agenda) |
||
(6 intermediate revisions by the same user not shown) | |||
Line 5: | Line 5: | ||
=Agenda= | =Agenda= | ||
*'''Preparation of parts for ECAL''' -- Sasha | *'''Preparation of parts for ECAL''' -- Sasha | ||
− | * | + | ** - HV long cable: Sammy and Mindy have to assemble 10 cables |
− | * | + | ** - HV distribution boards. Chris has completed the design of the HV distribution boards. We met with Chris, Tim, and Scot regarding location of the boards on the detector frame |
+ | ** - LED: Started testing the prototype of the LMS (need to make the detector room light tight) | ||
+ | <!-- ** - [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/05_10_2024/May-10-2024-L.pdf Update from Laveen] --> | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | ||
− | * ''' | + | ** Report from students [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_28_2024/student_report_06_28_2024.pptx] |
+ | ** Installation of HV cables [https://logbooks.jlab.org/entry/4313492] | ||
+ | ** Installation and testing cables and dividers [https://logbooks.jlab.org/entry/4313507] | ||
+ | ** Installation of long signal cables [https://logbooks.jlab.org/entry/4312667] | ||
+ | ** Installation LV patch panels and cables [https://logbooks.jlab.org/entry/4312759] | ||
+ | ** Installation of optical fibers [https://logbooks.jlab.org/entry/4311499] | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | ** [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/Document_240716_195013-1.pdf Safety briefings] | ||
+ | * '''Students''' -- Sasha | ||
+ | ** - Expect one student from Wuhan, paperwork is in process. | ||
* '''Beam tests with the PS''' | * '''Beam tests with the PS''' | ||
+ | *** measure shower beam profile and reconstruction in the crystal/LG transition region | ||
+ | *** (install prototype with 5x5 PbWO4 modules + ? LG) | ||
* '''Other hardware projects''' | * '''Other hardware projects''' | ||
+ | ** prototype of the ECAL veto counter (?) | ||
*'''Analysis/Simulation''' | *'''Analysis/Simulation''' |
Latest revision as of 09:23, 26 July 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - HV long cable: Sammy and Mindy have to assemble 10 cables
- - HV distribution boards. Chris has completed the design of the HV distribution boards. We met with Chris, Tim, and Scot regarding location of the boards on the detector frame
- - LED: Started testing the prototype of the LMS (need to make the detector room light tight)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Report from students [1]
- Installation of HV cables [2]
- Installation and testing cables and dividers [3]
- Installation of long signal cables [4]
- Installation LV patch panels and cables [5]
- Installation of optical fibers [6]
- Detector installation page
- Safety briefings
- Students -- Sasha
- - Expect one student from Wuhan, paperwork is in process.
- Beam tests with the PS
- measure shower beam profile and reconstruction in the crystal/LG transition region
- (install prototype with 5x5 PbWO4 modules + ? LG)
- Other hardware projects
- prototype of the ECAL veto counter (?)
- Analysis/Simulation