Difference between revisions of "JEF meeting, July 26, 2024"
From GlueXWiki
(→Agenda) |
|||
Line 8: | Line 8: | ||
** - HV distribution boards. Chris has completed the design of the HV distribution boards. We met with Chris, Tim, and Scot regarding location of the boards on the detector frame | ** - HV distribution boards. Chris has completed the design of the HV distribution boards. We met with Chris, Tim, and Scot regarding location of the boards on the detector frame | ||
** - LED: Started testing the prototype of the LMS (need to make the detector room light tight) | ** - LED: Started testing the prototype of the LMS (need to make the detector room light tight) | ||
− | |||
<!-- ** - [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/05_10_2024/May-10-2024-L.pdf Update from Laveen] --> | <!-- ** - [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/05_10_2024/May-10-2024-L.pdf Update from Laveen] --> | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen |
Revision as of 09:18, 26 July 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - HV long cable: Sammy and Mindy have to assemble 10 cables
- - HV distribution boards. Chris has completed the design of the HV distribution boards. We met with Chris, Tim, and Scot regarding location of the boards on the detector frame
- - LED: Started testing the prototype of the LMS (need to make the detector room light tight)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Report from students [1]
- Installation and testing cables and dividers [2][3]
- Installation of long signal cables [4]
- Installing LV patch panels and cables [5]
- Installation of optical fibers [6]
- Detector installation page
- Safety briefings
- Summer students -- Sasha
- - Olivia, Ben, and Shane are on site. Expect one student from Wuhan (have to start with the paperwork)
- - Projects: document all test results, assist with the cable/divider installation, install signal cables on patch panel, work on the ECAL monitoring plots
- Beam tests with the PS
- measure shower beam profile and reconstruction in the crystal/LG transition region
- (install prototype with 5x5 PbWO4 modules + ? LG)
- Other hardware projects
- prototype of the ECAL veto counter (?)
- Analysis/Simulation