Difference between revisions of "May 07, 2024 KLONG CPS Design Meeting"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 13: | Line 13: | ||
*** Current Z locations [[media:CPS Z locations.pdf]] | *** Current Z locations [[media:CPS Z locations.pdf]] | ||
*** possible moving plan https://www.aerogo.com/products/air-caster-rigging-system/ | *** possible moving plan https://www.aerogo.com/products/air-caster-rigging-system/ | ||
+ | **** Concerms with dust/contamination - Tim to work with ES&H | ||
* Baseline KLF schedule [[media:KLONG Baseline Schedule with MRI.pdf]] | * Baseline KLF schedule [[media:KLONG Baseline Schedule with MRI.pdf]] | ||
* Power supply status - On order, due March 2025 | * Power supply status - On order, due March 2025 |
Revision as of 14:42, 6 May 2024
Meeting Time and Place
Tuesday, May 07, 2024, 1:00pm Hall D Counting House
- Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Pavel Degtiarenko, Tim Whitlatch, Eugene Chudakov, Josh Ballard
Agenda
- Review minutes from last meeting https://halldweb.jlab.org/wiki/index.php/April_23,_2024_KLONG_CPS_Design_Meeting
- Review new basic 3D model
- Copper Absorber geometry for Fluka?
- New radiation levels? Pavel
- Layout of magnet and components (Stephanie/Keith)
- Current Z locations media:CPS Z locations.pdf
- possible moving plan https://www.aerogo.com/products/air-caster-rigging-system/
- Concerms with dust/contamination - Tim to work with ES&H
- Baseline KLF schedule media:KLONG Baseline Schedule with MRI.pdf
- Power supply status - On order, due March 2025
- Magnet update (Josh/Stephanie)
- Can we use less expensive resin? What is the actual expected radiation levels at coils now?
- Can we use tagger magnet LCW (goes upstairs - is radiation an issue?)
- Copper cooling update -
- Status of brazing sample test media:CPS Absorber cooling test sample.pdf
- Lead brick painting is out for bid, bids due back this week
- DeGauss test summer 2024
- June - items due from ERR
- Thermal cycling of tungsten and copper write up - in work (Tim)