Difference between revisions of "JEF meeting, January 26, 2024"
From GlueXWiki
m (→Agenda) |
|||
(7 intermediate revisions by one other user not shown) | |||
Line 7: | Line 7: | ||
*'''Preparation of parts for ECAL''' -- Sasha | *'''Preparation of parts for ECAL''' -- Sasha | ||
+ | ** - signal cables - done | ||
+ | ** - signal patch panel [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done | ||
+ | ** - HV cables: received 1280 in total | ||
+ | ** - HV distribution boards: in preparation | ||
+ | ** - LV cables: Received 48 cables during this week | ||
+ | ** - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors [https://halldweb.jlab.org/detectors/fcal2/cables/lv_distribution/lv_dist_board.jpg ] | ||
+ | ** - Optical fibers and parts for the trigger/DAQ have been ordered | ||
* '''Ongoing projects''' -- Sasha, all | * '''Ongoing projects''' -- Sasha, all | ||
− | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | + | ** - Testing and labeling cables [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_3_2023/aoran_cables.jpg ], 120 short HV cables testes and labeled during this week. |
− | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad | + | ** - Prepare modules for the TAC and prototypes (using crystals with some imperfections) |
− | * | + | *** 26 modules for TAC [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/tac_mod.jpg] and 35 modules [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/prot_mod.jpg] for the beam tests are ready |
+ | ** - Preparation of the LMS | ||
+ | *** - Need to glue Al flange to the optical fiber | ||
+ | *** - Ready for installation [https://halldweb.jlab.org/detectors/fcal2/lms/installation] | ||
+ | ** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests] | ||
+ | *** Finished tests, working on the tech note | ||
+ | ** - [https://halldweb.jlab.org/detectors/AL/HallD_Racks Inventory database and GUI for installed electronics ] | ||
+ | ** - [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] | ||
+ | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Aoran | ||
+ | ** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx] | ||
+ | ** - Tested 637 divider (all fabricated dividers) [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers]. No dividers produced during this week. | ||
+ | ** - Spare PMTs, have about 20, likely need more for the future (order 30 more )? | ||
+ | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob | ||
+ | ** Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg] | ||
+ | ** Installation of the LMS | ||
+ | *** Started yesterday (after long delay) [https://logbooks.jlab.org/entry/4243052] | ||
+ | *** Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas) | ||
+ | ** Cable and divider installation | ||
+ | *** Started yesterday, making a decision how to stretch them [https://logbooks.jlab.org/entry/4243888] | ||
+ | ** Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ) | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | |||
+ | <!-- ** [https://halldweb.jlab.org/wiki/index.php/Detector_Alignment Detector survey] --> | ||
+ | |||
+ | =Minutes= | ||
+ | Attendees: Stjepan, Vlad, Sasha, Liping, Bill, Zisis, Igal, Jon, Malte, Olga, Jane, Phil, S.T. | ||
+ | * Installation of LMS is ongoing | ||
+ | ** Fibers have been routed and secured on integrating sphere side, to be connected soon | ||
+ | ** Checked fiber transmission with blue led light before gluing on detector side | ||
+ | *** Can glue ~10/hour | ||
+ | ** Used electrical tape on flange at detector side for light tightness | ||
+ | ** Using plastic clamps to organize fiber bundles coming off detector side | ||
+ | ** Bottom half fibers routed downward, upper half split left-right | ||
+ | * First batch of short LV cables finally arrived | ||
+ | * LV distribution boards arrived, need to be populated with connectors | ||
+ | * Plan in place for how to attach short cables in bundles of 6 or 7 to chains | ||
+ | * Divider tests stalled due to fabrication bottleneck | ||
+ | ** Once populated detector support group can help | ||
+ | * Stjepan is running simulations of various η decay channels with branching ratios comparable to η→π0γγ |
Latest revision as of 09:13, 29 January 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV cables: received 1280 in total
- - HV distribution boards: in preparation
- - LV cables: Received 48 cables during this week
- - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors [2]
- - Optical fibers and parts for the trigger/DAQ have been ordered
- Ongoing projects -- Sasha, all
- - Testing and labeling cables [3], 120 short HV cables testes and labeled during this week.
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
- - Preparation of the LMS
- - Need to glue Al flange to the optical fiber
- - Ready for installation [6]
- - Radiation tests of the PMT active base [7]
- Finished tests, working on the tech note
- - Inventory database and GUI for installed electronics
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / Aoran
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Detector installation [10][11][12]
- Installation of the LMS
- Started yesterday (after long delay) [13]
- Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas)
- Cable and divider installation
- Started yesterday, making a decision how to stretch them [14]
- Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)
- Detector installation page
Minutes
Attendees: Stjepan, Vlad, Sasha, Liping, Bill, Zisis, Igal, Jon, Malte, Olga, Jane, Phil, S.T.
- Installation of LMS is ongoing
- Fibers have been routed and secured on integrating sphere side, to be connected soon
- Checked fiber transmission with blue led light before gluing on detector side
- Can glue ~10/hour
- Used electrical tape on flange at detector side for light tightness
- Using plastic clamps to organize fiber bundles coming off detector side
- Bottom half fibers routed downward, upper half split left-right
- First batch of short LV cables finally arrived
- LV distribution boards arrived, need to be populated with connectors
- Plan in place for how to attach short cables in bundles of 6 or 7 to chains
- Divider tests stalled due to fabrication bottleneck
- Once populated detector support group can help
- Stjepan is running simulations of various η decay channels with branching ratios comparable to η→π0γγ