Difference between revisions of "JEF meeting, January 6, 2022"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 14: | Line 14: | ||
** Disassembling CCAL | ** Disassembling CCAL | ||
*** CCAL moved to the ESB | *** CCAL moved to the ESB | ||
− | *** All modules (with SICCAS crystals) are removed | + | *** [[All modules (with SICCAS crystals) are removed]] |
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf List of available parts] | ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf List of available parts] | ||
* '''Module fabrication''' -- Sasha | * '''Module fabrication''' -- Sasha |
Revision as of 00:10, 6 January 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Preparation of parts for FCAL2 modules -- Sasha
- Received all 150 CRYTUR crystals from physics division (22-C0275) [1]
- Wrapped CRYTUR crystals: 825
- 10 crystals wrapped since last meeting
- Available for wrapping: 10 CRYTUR crystals
- Mindy (DSG group) continues wrapping crystals and soldering wires to sockets
- Disassembling CCAL
- CCAL moved to the ESB
- All modules (with SICCAS crystals) are removed
- List of available parts
- Module fabrication -- Sasha
- Status of fabrication
- Fabricated modules: Total 1378 (7 modules fabricated since last week)
- Testing of PMT dividers -- Sasha / Arshak
- Installation of the FCAL2 detector -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [2]
- Detector cabling and patch panels for the FCAL insert
- Manpower and division of tasks
- Projects for summer students
- Light Monitoring System -- Arshak
- Simulations/Analysis