Difference between revisions of "JEF meeting, September 30, 2022"
From GlueXWiki
(5 intermediate revisions by one other user not shown) | |||
Line 13: | Line 13: | ||
*** Available for wrapping: 722 - 707 = 15 | *** Available for wrapping: 722 - 707 = 15 | ||
*** DSG group continues wrapping | *** DSG group continues wrapping | ||
+ | ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf List of available parts] | ||
* Module fabrication -- Sasha | * Module fabrication -- Sasha | ||
+ | ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] | ||
+ | ** Fabricated modules: <span style="color:#FF0000"> Total 1247 </span> (25 modules fabricated since last week) | ||
+ | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All SICCAS 576 SICCAS] | ||
+ | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 671 CRYTUR], available: 51 | ||
* Updates from the FCAL installation meetings with Tim's group -- Sasha | * Updates from the FCAL installation meetings with Tim's group -- Sasha | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Installation_Meetings September 21] | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings Link to the earlier design meetings] | ||
* Light Monitoring System -- Arshak | * Light Monitoring System -- Arshak | ||
+ | |||
+ | =Minutes= | ||
+ | Attendees: Olga, Sasha, Arshak, Bill, Phil, Axel, Azizah, Igal, S.T. | ||
+ | |||
+ | * Received last batch of PMTs -- now have 1610 in total + 144 in COMCAL | ||
+ | ** Olga, Igla, Sasha did pre-selection based on diameter and traded with NPS | ||
+ | * Have 1400 light guides, need 200 more | ||
+ | * Have 75 PMT housings (have been annealed) of 300 needed | ||
+ | ** Need to check diameters | ||
+ | * Crystal wrapping continues. As of the meeting 5 were left over needing wrapping | ||
+ | * Expect 105 crystals from JLab pool + 50 more to arrive next month | ||
+ | * Week of 10/3, Sasha expects to find time to work on PMT dividers | ||
+ | ** Contract with GWU for divider work | ||
+ | ** Need to check for possible noise problems seen by NPS (but they are using a higher amplifier gain than we expect to use) | ||
+ | * Engineering/installation meetings now biweekly | ||
+ | ** Discussing cabling (using thin RG-XX cables (not sure of the number)) | ||
+ | ** Discussing unstacking and storage of lead glass blocks | ||
+ | ** Discussed connection plan for crates for insert | ||
+ | * Sasha mentioned need for students in the late spring/summer of next year |
Latest revision as of 13:38, 3 October 2022
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- Received 100 PMTs (the last batch) [1]
- All PMTs have been checked (measured diameter)
- 39 PMTs were exchanged with the NPS (they are slightly tight)
- Wrapped CRYTUR crystals: 707 (15 since last week)
- Available for wrapping: 722 - 707 = 15
- DSG group continues wrapping
- List of available parts
- Received 100 PMTs (the last batch) [1]
- Module fabrication -- Sasha
- Status of fabrication
- Fabricated modules: Total 1247 (25 modules fabricated since last week)
- All SICCAS 576 SICCAS
- 671 CRYTUR, available: 51
- Updates from the FCAL installation meetings with Tim's group -- Sasha
- Light Monitoring System -- Arshak
Minutes
Attendees: Olga, Sasha, Arshak, Bill, Phil, Axel, Azizah, Igal, S.T.
- Received last batch of PMTs -- now have 1610 in total + 144 in COMCAL
- Olga, Igla, Sasha did pre-selection based on diameter and traded with NPS
- Have 1400 light guides, need 200 more
- Have 75 PMT housings (have been annealed) of 300 needed
- Need to check diameters
- Crystal wrapping continues. As of the meeting 5 were left over needing wrapping
- Expect 105 crystals from JLab pool + 50 more to arrive next month
- Week of 10/3, Sasha expects to find time to work on PMT dividers
- Contract with GWU for divider work
- Need to check for possible noise problems seen by NPS (but they are using a higher amplifier gain than we expect to use)
- Engineering/installation meetings now biweekly
- Discussing cabling (using thin RG-XX cables (not sure of the number))
- Discussing unstacking and storage of lead glass blocks
- Discussed connection plan for crates for insert
- Sasha mentioned need for students in the late spring/summer of next year