Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- Received 100 PMTs (the last batch) [1]
- All PMTs have been checked (measured diameter)
- 39 PMTs were exchanged with the NPS (they are slightly tight)
- Wrapped CRYTUR crystals: 707 (15 since last week)
- Available for wrapping: 722 - 707 = 15
- DSG group continues wrapping
- List of available parts
- Received 100 PMTs (the last batch) [1]
- Module fabrication -- Sasha
- Status of fabrication
- Fabricated modules: Total 1247 (25 modules fabricated since last week)
- All SICCAS 576 SICCAS
- 671 CRYTUR, available: 51
- Updates from the FCAL installation meetings with Tim's group -- Sasha
- Light Monitoring System -- Arshak