Line 13: | Line 13: | ||
*** Available for wrapping: 722 - 707 = 15 | *** Available for wrapping: 722 - 707 = 15 | ||
*** DSG group continues wrapping | *** DSG group continues wrapping | ||
+ | ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf List of parts] | ||
* Module fabrication -- Sasha | * Module fabrication -- Sasha | ||
* Updates from the FCAL installation meetings with Tim's group -- Sasha | * Updates from the FCAL installation meetings with Tim's group -- Sasha | ||
* Light Monitoring System -- Arshak | * Light Monitoring System -- Arshak |
Revision as of 10:44, 30 September 2022
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- Received 100 PMTs (the last batch) [1]
- All PMTs have been checked (measured diameter)
- 39 PMTs were exchanged with the NPS (they are slightly tight)
- Wrapped CRYTUR crystals: 707 (15 since last week)
- Available for wrapping: 722 - 707 = 15
- DSG group continues wrapping
- List of parts
- Received 100 PMTs (the last batch) [1]
- Module fabrication -- Sasha
- Updates from the FCAL installation meetings with Tim's group -- Sasha
- Light Monitoring System -- Arshak