Agenda

  • Announcements
  • Review of minutes from 24-Nov-2010 meeting
  • Coil test update - Elliott
  • Getting ready for upcoming tests - all
    • Multi-crate trigger test in Electronics lab
    • UConn test in Hall B
    • FCAL beam test
    • FDC cosmic ray test
  • IRMIS - Elliott
    • detector translation table
  • Raw event format - Dave
  • Event display - Elliott
    • event evio and danaevio input
  • Electronics update - Chris
  • Trigger update - Alex
  • DAQ update - Dave A
  • Other electronics, trigger and DAQ status reports - Fernando, Ben, Ed, Dave, William, Bryan


Time/Location

1:30 PM Wed 16-Feb-2011 CC F326


Announcements

Next Meeting

1:30 PM Wed 2-Apr-2011 CC F326


New Action Items from this Meeting

Minutes

Present: Elliott W, Beni Z, Simon T, Dave L, Alex S, Elton S, Yi Q, Bryan M, Hovanes E, Dave A.


Coil Test Update

  • Currently hunting down some vacuum leaks.
  • Otherwise everything about ready to go.
  • Expect faster cooldown, shorter testing period than with the first coil.


Upcoming Tests

  • UConn
    • have what they need for microscope test, likely will run in the fall.
    • may need to redesign preamp.
    • Elliott will fine computer for active collimator test.


  • High-speed multi-crate trigger/electronics test in Electronics lab
    • have begun collecting test equipment for use this spring.
    • Dave A will supply multi-core rack-mount computer, Elliott has monitor/keyboard/mouse.
    • firmware still under development, hardware mostly ok.
    • CODA3 eventually will be used, may use codaLite to get started.
    • will use Bryan and Dave's readout libraries in either case.
    • will use Linux rocs.


  • FCAL test
    • little known about purpose, timing, schedule, etc.


  • FDC test
    • Beni generated list of required hardware and timelines, test starts 6/2012 in EEL 126.
    • will NOT have new F1TDC's available, so must use old F1's.
    • Dave A located 23 old F1's in varying condition, Beni will select 8 good ones for use in the test.
    • need to develop a lot of software by then.
    • Elliott and Beni will generate note on requirements, timelines, milestones, etc.
    • need prototype system by Jan 2012.


IRMIS

  • Elliott is having MIS group install IRMIS on a development machine.
  • Developer used Glassfish, MIS uses JBoss, some incompatibilities noted.
  • Will evaluate using controls information from the solenoid coil test.


Raw Event Format

  • Dave L consulted with Carl T and Dave A on the EB output format.
  • Goal is to generate simulated evio output in online format by the summer.
  • Much discussion of event blocking, entangled events, where to unblock and disentangle, etc.


Event Display

  • Needed for FDC test, may use Java version.
  • Elliott needs to talk with Andrew about this.


ROC Evaluation

  • Readout libs work with all three boards tested.
  • DAQ group leaning towards GE board since it is the cheapest.
  • GE board also allows addition of 10 GBit Ethernet mezzanine card, probably needed for high luminosity running.
  • Board cost currently $3400 in small quantities, within our budget.
  • Likely to get discount for large purchase, but don't want to buy most of them until we're about to start running.