Minutes-6-18-2009
From GlueXWiki
FDC Weekly Meeting
Date: June 18, 2009
Participants: Daniel, Simon, Brian, Micah, Rich, Bill, Mark S., Beni, Fernando, Roger, Chuck
Next Meeting: June 25, 2009 @ 1:30 p.m.
Contents
General Construction Updates
- The fiber-reinforced gusset pieces have arrived from the shop. Each ring will be made from 8 arc pieces, with one ring on the upstream package face and one ring on the downstream package face. - The parts for the assembly jig on which the detector stack will be constructed are now being made in the machine shop. Their delivery is imminent. Once we have the pieces in hand, we will do some mechanical checks to see how everything fits together. - Bill will take on the preparation for a stack assembly document. A draft will be prepared before assembly of the full-scale prototype and then fleshed out during the process with relevant photographs taken. - Cable preparations: * The LV cables have arrived and will be tested in the near future. * The parts n' pieces for the HV cables are now all in hand and construction and testing will begin over the next several weeks. * The signal cables and connectors are in hand and Mark and Brian will begin construction as they have time. * We discussed how much of the outer jacket and braid will be stripped off the signal cables. The initial thought was to pull it off all the way to the upstream face of the magnet. We need to get some feedback from the BCAL folks on this. Fernando will post some information on this question on the wiki. - The o-ring material order has arrived. The material is a mixture of nitrile and EPDM (Ethylene Propylene). Its hardness is about 10 durometers. - We are now having short daily meeting to review the work on the full-scale prototype construction and to ensure that any snags or problems that come up are immediately addressed. - We discussed the time frame for preparing the upstream and downstream gas windows and their associated laminate frames. Bill thought that the laminations could be laid up next week and set aside for when we are ready to attach the aluminized mylar windows. - Mark S. will prepare the order for the cables that will be used to attach to the cathodes for the external ground. He will also order the sealing epoxy that is used to cover the conducting epoxy. This is a humidity protection plan recommended by Fernando. - Eugene is working to identify clean room space for FDC construction. He has talked recently with Dennis Skopik who will work to define the assigned space.
Wire Frame Update
- Armen has completed the soldering work on the four wire frames. All four frames were placed back in the Lucite box under nitrogen purge. - Rich has been performing HV tests on the frames one by one. Three frames have been tested with one to finish. The test amounts to applying 1kV to each bus and studying the current draw. A problem has been found with one bus on frame P3. Fernando and Rich will come back to this board and try to isolate the cause. More to come. Note that this electrical QA on the finished frames will be a standard part of QA on all wire frames. - We need to have a dedicated meeting to design what the schedule for work on the Phase 3 wire winding will be. The highest priority for work scheduling will be doing work on upgrades of the wire winding facility. This includes a better strongback design, the design and construction of precision combs, modification to the wire winding table, and a list of other items with the system. Stay tuned, more to come. - We are pushing hard to begin wire frame construction early next year and begin wire winding before the end of 2010. Hopefully this can all procede. We are now working to complete the simulation studies with Simon to determine if we want to offset neighboring wire layers. More to come in the upcoming months. - The wire frame construction document is located at: /u/group/halld/Engineering/PRELIMINARY DOCUMENTS. He will include the information on the wire electroplating process as well. - Bill is now designing the jig for the wire electroplating operation and it will be ready for submission to the shop at some point in the future. We will make a decision shortly if/when we will electroplate the wires for the full-scale prototype. - Brian received the SEM scans for our wire from the W&M folks. He will generate a final QA report with photos and test results for all wires in the next several weeks.
Cathode Update
- Progress updates: * The laminations for the 8 cathode frames have been completed. Work to seal the exposed Rohacell edges and drill and seal the gas ports is now underway. This is a relatively slow process that we can speed up with a bit of cleverness. * Cutting of the edges of the cathode boards is now nearly finished. Brian and Mark S. should be done by tomorrow with the full set. * We are working to finalize the procedure for laying up the 3 piece cathode panels. It appears we have a complete plan in place and a final mockup has been made with dummy boards. * A cathode panel lay up using a non-final procedure was completed and the quality is not superior, but it should be useable. The free transfer ring has been attached and the board is ready for tensioning. * Brian and Mark S. expect to lay up the next cathode panel tomorrow and should be able to complete 2 or 3 next week. * Eugene has retensioned the 2 micron board that was made a month ago. He set the average tension to ~500 N/m and saw a 2% tension change after 1+ day. Measuring 5 days later found no further tension changes. This board should have a frame attached this week and removed from the tensioning facility. * Micah and Mark S. have scanned the surface flatness of the 5 micron Cu board and Micah showed us some preliminary results that were encouraging. He wants to scan the granite table and subtract this data to give the final flatness measurements for this board. The 2 micron Cu board will be scanned next week. Note that this work occurred only after Bill spent significant time modifying the system to ensure the cathode boards were clamped flat to the granite table. - Brian will construct a bag that we can keep all completed cathodes in so that we can keep them in a nitrogen purge to prevent oxidation. The bag will allow the completed cathodes to be clamped so that the frames remain flat. - A portion of the rigid-flex assembly has arrived (50 each of the cathode boards and ground boards). The problem with the locating holes being to small (mentioned above for the wire frame PCBS) is present with these boards too. Roger will see to it that the holes are enlarged and the boards are passed on to Armen for soldering work early next week. Fernando has already alerted Armen so that he is ready to receive the boards. The remainder of the order will be delivered in about 2 weeks. - Bill has been working on the cathode construction document. He has circulated a draft for comment. The file is located at /u/group/halld/Engineering/PRELIMINARY DOCUMENTS. - We are working to finalize the PR for the 2 micron cathode board material. Procurement will be negotiating with Nippon Steel Chemical Company to try to convince them to complete this order. Roger is also in discussion with the company that makes the 5 micron Cu boards about making the 2 micron boards. Stayed tuned for new developments. - Roger needs to prepare a document for QA/stuffing/cleaning for the cathode boards and a similar document for the cathode daughter boards and ground boards.
Cooling System Tests
- Fernando is in the process of writing up the results from his cooling system studies. Stay tuned for the GlueX note. He indicated that he is back to work on this document and it should be done shortly.
Cosmic Ray Test Stand
- Beni is continuing work to setup the cosmic ray telescope and test system in EEL 126. He would like to have it all up and functioning and understood before the end of June. Progress is being made connecting up all detectors and getting CODA working. - We still have some mysterious behavior with the small-scale prototype response with wiggles in the X vs. Y distributions that need to be understood. We decided to have a separate meeting to discuss what work we would like to do on the small-scale prototype. - Beni has started a bench test plan for the full-scale prototype and we discussed his preliminary document briefly. He will circulate it for feedback and we will continue to flesh it out. We want to make sure that we do some checks of gas leakage with the prototype. We agreed that the best procedure would be to use the P5 gas mixture (non-flammable). - Bill has designed a system to rotate the prototype from vertical to horizontal. The drawings have been submitted to the machine shop and the pieces should be delivered in about 3 weeks. - Safety paperwork for the cosmic ray test stand is being prepared now and will be submitted to Bert shortly.
Work List
- The FDC short-term work list has been posted on the FDC web site. This is continually being updated and DSC welcomes any feedback or comments from the group.
Minutes prepared by Daniel. Send any comments or corrections along.