Minutes-4-3-2008
From GlueXWiki
FDC Weekly Meeting
Date: April 3, 2008
Participants: Daniel, Simon, Kim, Fernando, Elke, Roger, Mark, Jim
Next Meeting: April 10, 2008 @ 1:30 p.m.
Contents
- 1 Cathode Planning
- 2 Full-Scale Prototype
- 3 Test Frame Wire Winding
- 4 Stack Assembly Procedures
- 5 Composite Cathode Updates
- 6 Grounding Issues
- 7 Gas Volume Definition
- 8 STB/HVTB Discussion
- 9 Cathode Board Discussion
- 10 Small-Scale Prototype
- 11 ASIC Studies
- 12 Cathode Flatness Measurements
- 13 Tracking System Design Reviews
- 14 Miscellaneous
- 15 Drawings
- 16 Work List
Cathode Planning
- The nominal design of the FDC cathodes is 2 microns of copper on 1 mil of Kapton with a 2 mm Rohacell backing. In the current design, the ratio of materials copper/Kapton/Rohacell/epoxy is 32/20/36/12. Thus copper is not the dominant contributor. We are also worried about going to much thinner copper for two important reasons, namely the thinner the copper, the harder it is to solder to, and also, the thinner the copper, the more delicate the boards are and the more susceptible to damage they are. Thus we are going to attempt to stay close to our nominal design as we seek out a board supplier and a board house. - There are two technologies for manufacturing our cathode board material. The first is vacuum deposition. This process necessarily focussed on very thin copper layers (below a tenth of a micron say). It may not be possible to use this technique to prepare boards with 2 micron of copper, but it is worth investigating. The point is that 2 microns of copper from this approach is pushing the technology from above. The second approach for board manufacture is flashing on a thin layer of nickel and then a copper layer. This approach is more suitable for thicker layers (say above 5 microns). This our 2 micron copper thickness desire is pushing the technology from below. - The biggest issues in finding a material supplier are both the copper thickness AND the physical size of our boards. Of course, we would like to have our cathodes made from a single flex board, but even with our 3 piece design, we are really pushing what companies can provide. - We have learned recently from our Sheldahl sales representative, they they are not able to prepare our nominal cathode materials for the time being as they are reorganizing their production lines. Roger will be the sole contact with them. He will communicate with both the Sheldahl sales representative as well as the technical folks. The question is, when will they be able to supply something close to our board material? We would be willing to purchase the full amount of this material, for both the full-scale prototype, as well as the production cathodes. - Jim raised the idea of purchasing flex boards with thicker copper layers and then plasma etching them down to our requirement. He said that this approach has been used before. Jim will make a list of contacts and provide them to us. Kim will take responsibility for being the contact point on this front. - Even though vacuum deposition is usually used to prepare flex boards will very thin copper, we should not rule out invesigating whether we can use this approach for our nominal boards. - Jim will talk to his contacts in Germany to prepare us a list of sales representatives and company contacts so that we can start to make some in roads toward finding both a material supplier and a board house. Kim will be the contact point for dealing with the companies that are provided. - DSC will prepare a specification document for the cathodes, including tolerances, and supply this to Kim and Jim. After we find one or (hopefully) more companies that might be able to provide what we need, we will then start discussion of our handling requirements with them. DSC has already prepared a document for the handling requirements.
Full-Scale Prototype
- The Rohacell order arrived on Tuesday of this week. As Brian was away today, we do not know the status or expected delivery date of the G10 order. DSC will work with Brian to prepare a construction time line for the wire frames so that they are ready to go to IUCF for the Phase 2 shortly after the completion of the Phase 1 winding. - The 50-pin connectors have all arrived (for both the chamber end and the electronics end). - All wire frames PCBs have arrived and passed our QA checks. All sets that were to be stuffed by Greg Arnold's group have been completed (Phase 1 stuffing only). Kim has delivered the completed boards to Simon for storage. - Kim has received the ERNI connectors. The HV capacitors are expected to arrive by the end of May. - The order for the cathode rigid flex boards has gone out and should be delivered early next week. The cathode ground boards will arrive in about 2 weeks. - No progress has occurred on modifying the aluminum construction jig as Brian has not yet gotten to this. Hopefully we can converge on completing this work before Brian goes to IUCF. - DSC and Brian talked to Jack Segal about occupancy of the clean tent in the EEL building. We are expecting to have occupancy at some point in the first part of this month. More details to come. Brian needs to order the second construction station for the full-scale prototype construction.
Test Frame Wire Winding
- DSC has been in daily contact with IUCF as they prepare to begin the wire winding procedure for Phase 1. They believe that the wire winding system is essentially ready and they are working on preparing the wire placement measurement system and the tension measurement system. They have laid out the design for a support frame and will have this made at the IUCF shop as they can get it done before we could and they need this before Brian can go out there. - We have shipped IUCF two of our wire frames and the aluminum strongback. Hopefully this will arrive in Bloomington on Tuesday or Wednesday of next week. - They are hoping to be ready for Brian now on the week of April 13, but they believe that this may already be too tight, and that the week of April 20 is more likely. They will give us feedback as soon as they know. - DSC is working with Steve Christo to prepare a wire specification document for the tungsten and CuBe wires leading up to procurement. Steve is preparing a document for the Hall B chambers and we will most likely adopt this document for Hall D. DSC reviewed the existing Hall B documents to give folks a flavor of how these documents have been prepared in the past. We need to make decisions on what is required for the FDCs.
Stack Assembly Procedures
- DSC, Brian, Tim, and Bill will work to finalize the stack assembly construction document that has been prepared. This document should be in place before we get too far in the construction process.
Composite Cathode Updates
- No progress on completing the composite cathode cathode sandwich as Brian has been away most of the week. This prototype will be worked on to finalize the Rohacell sealing procedure, the ground plane attachment procedure (including connections to the outside), and attachment of the gas ports.
Grounding Issues
- Fernando will supply an overall grounding specification document very soon. He is working on it.
Gas Volume Definition
- Bill has been in contact with Dave Meekins as he continues to work on studies of our gas volume definition. Dave has recently got one of Bill's models to work. While the results are considered very preliminary, what seems to be coming out is that there are problems with the gas delivery with the model with only the central hole. There are clearly dead regions (or low flow regions) in the space between the ground plane and the cathodes. Clearly our design is not final and we will have to take the output from the these calculations, and perhaps from a real-world study of a prototype, to converge on a final design that will meet our requirements.
STB/HVTB Discussion
- Based on the work that Greg Arnold did, he will work with Kim to update the cleaning/assembly procedures document that Fernando initially came up with. Fernando's document will be modified to reflect what Greg's group actually could do. Fernando will review the marked up document and provide feedback on what we will ultimately be satisfied with. The question is what we can accept if the wire frame circuit boards are stuffed in house. If they are stuffed by an outside company, we will be able to ensure industry standards for handling and cleaning.
Cathode Board Discussion
- Roger has ordered a sample test setup that includes a G10 frame with a piece of a cathode board mockup for continued solder tests. His tests of soldering to a dummy cathode boards (covered completely with Copper) were not successful. There was too much of a heat sink. His approach was to use a small-tipped soldering iron. He did report that even at 800 deg on the iron, there was no trouble with the copper pealing off the Kapton backing. If the soldering approach does not work, Roger will move to a hot-air reflow technique. Given the new test fixture that he has ordered, he believes that he should be able to finalize the rigid flex board attachment. He will prepare a procedures document based on the final approach that he comes up with. - Roger needs to prepare a document for QA/stuffing/cleaning for the cathode boards and a similar document for the cathode daughter boards and ground boards. - Roger was planning to do some test soldering for the rigid flex cables to a sample cathode board. No update was given during the meeting.
Small-Scale Prototype
- During the past week, Simon's DAQ computer bit the dust (goodbye computer, we hardly knew ye). He has gotten another replacement and is getting everything working again. He mananged to collect about 3 days worth of data with the new 2 micron cathodes. As reported last week, it basically worked. However there are some problems in the calibrations that Simon has to figure out. - Simon's plan is to complete the studies with the current configuration (Hall B SIPs, charge-integrating ADCs, 90-10 mixture). He will then study the setup with the 40-60 mixture before putting the ASICS/FADCs back into the system. He will then move on to perform quantitative studies of the FDC dynamic range.
ASIC Studies
- We had a meeting earlier in the week on the measurement requirements with the CDC and FDC systems for the ASICs. We want to be able to get all required information to Mitch Newcomer so that he can make any and all design modifications for the ASICS to be able to meet the June submission deadline. Fernando is working to prepare a full test plan document that he will circulate early next week for feedback from the group.
Cathode Flatness Measurements
- The laser measurement system from Acquity Laser has arrived. What we got for a 30-day trial is a laser, a laser sensor, and a power supply box. There was also some documentation. - DSC would like to meet in the shop with the equipment, and with Brian and Bill to go over the plan for setting this system up. DSC is concerned with the current cathode construction procedure and the looseness of the cathode surface. When the plane is vertical, there is a noticeable concavity in the surface this is not acceptable. The question is whether the 2 mm backing is actually helping or doing what it should. Do we need to consider additional tensioning of the cathode boards before attachment to the frames, etc. The measurements of one of our cathode prototypes in the vertical position will help us to quantatively understand the scale of the gravitational sag of the boards.
Tracking System Design Reviews
- The final design review for the tracking chambers and particle identification system took place at JLab on March 27. This system reviewed the FDC and CDC systems, as well as timing in the BCAL and TOF systems. By all measures the review was a complete success, with no issues or major recommendations brought up during the review close out. The FDC design was essentially blessed and was not even mentioned during the close out period from the standpoint of issues at any level. - DSC wants to thank everyone who contributed to making this a successful review. Your time, energy, patience, and skills are fully appreciated.
Miscellaneous
- DSC is working to schedule combined CDC/FDC meetings, probably on Monday afternoons. This meeting will focus on combined mechanical and design issues for the two systems. - DSC is reviewing the FDC construction budget to give Elke any substantial changes (either down (yeh, really likely) or up). This work will be completed early next week after we get updates on the cathode rigid flex boards and the wire frame circuit boards.
Drawings
- DSC has collected all of the available FDC subsystem design drawings and placed them on the FDC website. The URL is: http://www.jlab.org/Hall-D/detector/fdc/drawings.html. Folks should go through the drawings and let DSC know what drawings and/or categories are missing for a complete design set. - Also folks should send DSC the latest design drawings where there have been changes to keep this web site up-to-date through the review season.
Work List
- The FDC short-term work list has been posted on the FDC web site (see http://www.jlab.org/Hall-D/detector/fdc/). This is continually being updated and DSC welcomes any feedback or comments from the group.
Minutes prepared by Daniel. Send any comments or corrections along.