Light Guide Rework Plan

From GlueXWiki
Jump to: navigation, search

DRAFT

  1. Second generation (new modules)
    • implement new gluing procedure on all new modules
    • monitor glue joints for 3 days before packing up
  2. First generation modules (old procedures used)
    • Fix the black spot problem before rework
    • Confirm list of detached light guides to be reworked
    • Reglue all light guides with detached light guides
    • illuminate guides showing no detachment with 50 s of UV light through the front
  3. Light guides
    • Lightly sand base with 600 grit paper.
    • If required to take off additional material, use 400 grit paper, then 600 grit.
    • Note: This process will be checked by Keith so ensure that 280 grit is not needed.
  4. Lifting
    • Setup/process for lifting tops off boxes
    • Tom has suggested and approved a process for lifting the tops
  5. Major rework
    • Treat in a similar way to new modules
    • Modules with major rework should be worked under the tent
    • These modules have been moved to the ESB for repair
    • Full testing after repairs are complete.
    • Monitor glue joints for 3 days before packing up. Note: continue monitoring 10 & 33 for a longer period
  6. Minor rework
    • Likely rework down in the hall
    • Move the tent down to the hall?
    • Illuminate guides with no rework with 50 s of UV light through the front
    • Visual check of LEDs when work is complete.
  7. Determination of detached status
    • "Detached" is to mean that an area corresponding to more than 8 fibers is separated.
    • On Monday, Bobby, Tina and Keith will independently make a visual evaluation of the detached status of light guides of modules on the floor of the ESB.
    • They will compare notes and, with Elton, come to a consensus of which light guides are to be classified as "detached"
    • Following this exercise, any of the three persons above, will make the determination of the light guide detached status
  8. Documentation
    • Feedback to Jim on his new procedures document
    • Finalize version 1 and place under document control
    • I have submitted the Pansophy Rework sheet to be added to the system
  9. Changes to the procedures
    • Any changes of procedures will have to be approved by Elton, or by Tim if Elton is not available.
    • Modifications will be made in consultation with all personnel working on the project.