June 17, 2021 CPP Design Meeting

From GlueXWiki
Jump to: navigation, search

Meeting Time and Place

Thursday Jun 17, 2021, 3:30pm Bluejeans https://bluejeans.com/465620466

  • Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I

Agenda

  • Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/June_17,_2021_CPP_Design_Meeting
  • Chamber delivery
    • OSP/Testing status - Beni
    • Gas system status - Tim
  • Cable routings
  • Design/Fab/Procurement status
    • Stand
    • Steel
    • Fcal platform mods
  • Things to work out
    • Gas system, manifold/bubblers (Beni has some)
    • Complete structural analysis
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements
    • Modified US vacuum system
    • Solid target installation
    • Installation drawing including Microscope move

Minutes and Action Items

  • Gas system tested and ready to go
  • Beni submitted final OSP for testing
  • 4 MWPCs in house and safe in EEL
  • Cable routing and length have been determined, Elton made a log entry
  • CPP Support stand in house in TEDF and will be pre-assembled
  • Preparing for floor rail survey and hole cutting of downstream platform
  • CPP absorber steel awarded and in work