JEF meeting, January 31, 2025
From GlueXWiki
Connection
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
- -New LMS light source is ready [1]. Will be installed and checked during next week. Parts for holding reference PMTs are ready.
-Installation of the FCAL2 detector & integration to GlueX -- Sasha, All
- Implementing ECAL into the GlueX DAQ [2]
- - Six VTPs have been installed, firmware loaded
- - Testing GTP trigger using individual ECAL VXS crates [3]
- Commissioning the entire detector using the LMS (signal waveforms)
- ECAL HV interlock check [6]
- HV module failed during cosmic run [7]
- Tuning HV settings [8]
- Material in front of the ECAL, TOF absorber [9][10]
- Temperature scan in the ECAL divider region [11][12][13]
- Preparing for the run -- Sasha
- Page for shift Takers
- ECAL in the Experimental Safety Assessment Document (ESAD)
- EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236)
Restoring PS test setup [19]
- Working on the plan for testing calorimeter prototype
ECAL commissioning -- Sasha, All
Calibrations
Preparations for readiness review
Minutes
Attendees: Drew, Bill, Sasha, Zhikun, Igal, Mac, Olga, Vlad, Liping, Zisis, S.T.
- New LMS light source with 25 LEDs prepared, ready to be installed on integrating sphere
- Want one more LMS run with current light source to monitor health of PMT dividers
- Cosmic data used to determine new set of HV settings (3rd iteration)
- New fans have been installed
- Temporary temperature sensors installed in gap between chains to check impact of air flow
- HV moduled failed, has been replaced
- Need to set HV voltage timeout parameter to reduce frequency of tripping due to mismatched voltages
- Mini Readiness Review for ECAL/FCAL-2 set for February 14
- Hakob will arrive in February