JEF meeting, August 23, 2024
From GlueXWiki
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- - two remaining bundle of cables will be ready in about a week
- Installation and testing cables and dividers [7]
- Installation of long signal cables [8]
- Installation LV patch panels and cables [9]
- Installation of optical fibers [10]
- Detector installation page
- Safety briefings
- Students -- Sasha
- - Expect one student from Wuhan, waiting for the US visa
- Beam tests with the PS
- measure shower beam profile and reconstruction in the crystal/LG transition region
- (install prototype with 5x5 PbWO4 modules + ? LG)
- Other hardware projects
- prototype of the ECAL veto counter (?)
- Analysis/Simulation
Minutes
Attendees: Bill, Zisis, Axel, Laveen, Sasha, Stjepan, S.T.
- Waiting for 4 HV distribution boards
- Will be placed in boxes outside detector dark room with feedthroughs for cables
- estimated time of arrival unknown
- 2 bundles of HV cables installed, 2 more bundles almost ready
- Need to address problems with LV distribution boards
- Still using temporary light source for LMS, but final board design ready
- Need to fix some issues with optical fibers
- PMT divider/cable installation in insert continues
- Completion of last 4 layers to go
- Cable gap between top half and bottom half needed to be adjusted
- Added some space for velcro straps to secure chains
- Now installing by column
- 95 dividers to go, goal is to finish by end of August
- Integration of FCAL-2 into DAQ will start in September
- ECAL will be separate DAQ component similar to CCAL
- Will use new VTP module, new firmware needed
- Need to work on calibration plan outline/document