Hall D MEDCON5 Operations Resumption Status
Contents
- 1 Meeting Time and Location
- 2 Introduction
- 3 General Timing of Work in the Hall
- 4 Immediate Return June 8
- 5 June 9 Plan
- 6 First Tier - June 10
- 7 June 11
- 8 2nd Tier (Partial- mechanical only)- June 12
- 9 June 15
- 10 June 16 2nd Tier approval for all activities
- 11 June 17
- 12 June 18
- 13 June 19
- 14 June 22
- 15 3rd Tier (only as approved by Eugene) - June 23
- 16 June 24
- 17 June 25
- 18 Jun 26
- 19 June 29
- 20 June 30
- 21 July 1
- 22 July 2
- 23 July 6
- 24 July 7
- 25 July 8
- 26 July 9
- 27 July 10
- 28 July 13
- 29 July 14
- 30 July 15
- 31 July 16
- 32 July 17
- 33 July 20
- 34 July21
- 35 July 22
- 36 July 23
- 37 July 24
- 38 July 25-26
- 39 July 27
- 40 July 28
- 41 July 29
- 42 July 30
- 43 July 31
- 44 Upcoming work
- 45 References
Meeting Time and Location
4pm Daily (weekdays only) beginning June 8 on Bluejeans
Last updated July 29 15:09
https://bluejeans.com/465620466
Introduction
Jefferson Lab will be going into MEDCON5 status on Monday June 8 with the expectation of resuming beam delivery to the Halls in July. There will be a gradual ramp up of activity in the Hall D complex over several weeks. On June 8th, a limited staff will come in to ready the areas for personnel return to conform to JLAB requirements and to ensure the risk to personnel is as low as reasonably possible. Other tasks (and associated personnel) will be accomplished in Tiers in order to limit the amount of personnel in any given area and ensure the 6' distancing can be maintained. There is currently no work authorized in Hall D which requires this distancing to be violated. The Hall D complex will be set up to have one way traffic to minimize chance encounters. The description of this set up can be found in the Hall D Resumption Plan (See Link in References below).
This page will be updated daily after the 4pm meeting to reflect the following days work.
Access
In order to access the JLAB property, you must have your supervisors approval. Several actions must be completed prior to starting work;
- Everyone is to perform the Health Self Certification Test using the JLAB provided card daily before entering JLAB property. If you will not see your supervisor at the lab, send an email or text to your supervisor stating the results of your self certification.
- Anyone coming into Hall D must have the approval of the Hall D Group Leader, Work Coordinator or Engineer. This is daily.
- Sign in on the board at the entrance to the Counting House
- The COVID-19 Pandemic Controls OSP must be read and understood prior to coming to JLAB (See Link in References below)
- SAF003 COVID-19 Hazard Awareness and Controls must be completed (See Link in References below)
- Read and sign the general Pre-Job Check List for COVID-19 that will be posted in the counting house
- Complete and sign (persons performing task and their supervisor) the Pre-job checklist from the COVID-19 OSP for each task for which there is a written procedure before starting. The signed copy is to be posted at the job site.'
General Timing of Work in the Hall
Immediate Return June 8
-
Eugene Chudakov and Mark Stevens will do a morning walkthrough the Hall D complex to determine the status of everything and Meet with management to discuss next steps -
Mark Stevens and Josh Foyles will then ready the Hall D complex for personnel to return to get equipment ready for beam which includes all signage and documentation posted, reviewed and ready. Task list here File:Hall D Pre-First Tier Tasks.pdf
June 9 Plan
Mark And Josh will continue to get the area ready per checklist. No one else will come in
First Tier - June 10
Josh and Mark will go in 8am, Scot and Tim will go in 8:30 for briefing. Mark will transfer the Work Coordinator phone to Scot who will be the acting WC for several days. Mark and Tim will leave and Bobby will come in to get briefed on the situation and sign paperwork.
The work will consist of getting all the electronics cooling and gas systems operating at nominal conditions. This may take several days
-
ComCal:- Restore N2 purge to run value.
- Restore and reactivate chiller (refer to Hall D Procedure above)
- Detector apparatus cooling (follow checklist(s))
- Turn on Microscope fan
- Bcal readout N2 purge – increase to run value
- CDC blower – turn back on
- BCAL chillers (refill circuits and start chillers) (refer to Hall D Procedure above)
-
FDC chiller – turn back on and check proper operation (refer to Hall D Procedure above).
- Check operation of DAQ system in Counting House machine room
All cooling systems are up except BCAL chillers. This will be completed tomorrow.
Detector Gas Supply argon/CO2 (will be checked by Beni and Lubomir next week
June 11
Scot, Josh and Bobby authorized to come in to complete getting the BCAL chillers up and running
2nd Tier (Partial- mechanical only)- June 12
Scot, Keith and Chris will start working the DIRC - they all are authorized to come in
- Check N2 purge rate to Bar Boxes
- Restart the DIRC water cart.
- Refill upper Optical Box with purified water, adding new water to the system as required.
Chris Keith will come in for approximately 1 hour to check the target compressor and vacuum pump.
2nd Tier will consist of getting all vacuum systems, magnet systems, DIRC Water system, Target up and turning detectors on (crates HV and LV)and spread out over several weeks
June 15
Mark, Keith and Chris will continue working the DIRC - they all are authorized to come in
-
Fill lower optical box - Check entire systems for leaks - set flow to each box to 0.2 GPM
- Obtain water samples as directed.
- Get RadCon to release all water samples from the Hall.
-
Reduce Optical Box purge to run values. - Replace water filters on cart (later)
- Replace UV lamps on cart
-
Replace filters on upper and lower air cooling systems (later)
Others have not been approved for this day
June 16 2nd Tier approval for all activities
Mark, Keith and Chris will continue working the DIRC - they all are authorized to come in
-
Replace water filters on cart - Obtain water samples as directed. (later)
- Get RadCon to release all water samples from the Hall.
-
Replace UV lamps on cart - change DIRC air filters
Nick Sandoval will come in to turn on some of the crates</s> All turned on except Microscope
Others have been approved for this day - Mark Dalton, Beni and Lubomir, but they will wait until Wednesday to come in with Eugene
June 17
Scot and Bobby will come in to start working on magnet power supply check outs - they all are authorized to come in
-
Accomplish the Hall D Solenoid Magnet Interlock Checklist - Accomplish the Hall D Pair Spectrometer Magnet Power Supply Maintenance Turn-on Checklist
- Accomplish the Hall D Sweep Magnet Power Supply Turn on Checklist
- Nick turn on Microscope crate
Josh will come in to support chain hoist inspection
Mark Dalton, Beni and Lubomir will come in to get briefing from Eugene
June 18
Mark, Scot and Bobby will come in to ramp Pair Spec and sweep magnet power supplies - Nick may come in also - they all are authorized to come in
Lubomir and Beni checked/adjusted FDC and CDC gas system flows
June 19
Scot, Keith and Chris will come in to start bringing beamline vacuum system up
-
Turn on or verify normal operation of Goniometer pump - Turn on or verify normal operation of Tagger vacuum pump
- Turn on or verify normal operation of 10” beam pipe (between Tagger Vault and Collimator Cave)
- Turn on or verify normal operation of Collimator Cave vacuum pumps
- Turn on or verify normal operation of Upstream Platform beamline vacuum pumps
- Fcal (downstream) Platform beam pipe – reconnect pump and pump down (wait until Later
Tim will come in to send back mu metal shields to vendor and review Solenoid HCO paperwork
June 22
Mark, Josh and Bobby will come in to change out the aluminized Mylar seal on Solenoid 16psi relief tree.
3rd Tier (only as approved by Eugene) - June 23
Josh, Chris and Scot come in to do maintenance on the flood gates in the morning
June 24
Mark, Josh and Chris to do the Tagger LCW filters in the morning
Mark Loewus with contractor will be inspecting crane
June 25
Electrical load reduction 1:45-3:15, do crates need to be off?
Scot, Bobby and Tim to start on the Solenoid HCO
Nick will assist probably remotely
Check CPP lead installation possibilities
Jun 26
Mark, Keith and Chris come in the morning for solenoid vacuum checkout procedure
DIRC water samples taken and sent out for analysis
June 29
Scot and Josh Daily Walk Through and miscellaneous
Change CO2 bottles, knock down elephant trunk, fire safety walkthrough
Sasha came in, log entry made, BCAL chillers stopped cooling
Beni, Lubomir and Sasha will start cosmic runs and trigger
June 30
Tim, Scot and Bobby to do daily walkthrough and start Solenoid HCO
Sasha to come in to work on trigger ( all chillers operating now)
July 1
Scot and Keith to do daily walkthrough and miscellaneous
Sasha to come in to work on trigger
July 2
Mark and Chris to do daily walkthrough
Erect solenoid US safety fence
July 6
Mark, Bobby to do daily walkthrough, turn on BDX power and AC and check solenoid ground fault
Cosmics running
MCC will now have an operator in the control room 24 hrs
July 7
Josh and Chris to do daily walkthrough and continue HCO
Justin and Bill coming around 9am to check out DIRC
Lubomir to check gas analyzer and increase CDC flow 20.0000% +/- .0001%
July 8
Mark, Keith and Bobby to do daily walkthrough and Vacuum HCO (except FCAL Platform)
Jon Zarling working remotely on DAQ in morning
Sasha coming in afternoon to work on ComCal in counting room
July 9
Tim, Mark, Bobby coming in, Walkthrough, additional HCO
Ramp solenoid to 800A
Turn on Tagger NMR
Check Tagger Turbo shielding
Josh will come in 1st thing in the morning to snoop (leak) test the gas analyzer
Sasha in in afternoon
Nick in to check active collimator for new mods
July 10
Josh, Keith, Chris Walkthrough and HCO
July 13
Mark, Bobby and Keith Walkthrough and HCO
Sasha work on ComCal
Facilities replace lights in tagger
BCAL chillers to 41F
July 14
Scot, Josh and Chris Walkthrough and HCO
Sasha ComCal
July 15
Mark, Keith and Chris walkthrough and HCO
Valve in Alcohol bubbler
Zero NMR pobe
Colin 10am to sign paperwork and briefing from Mark
Chris Keith (5pm target vacuum)
July 16
Scot, Josh and Bobby for walkthrough and HCO
Valve out Alcohol bubbler (off)
Tim come in to review Relief valve test procedure - decided to wait until SAD
Sasha FADC
July 17
Mark, Keith and Josh for walkthrough and HCO
Hovanes come in to exercise ComCal and TAC
Lubomir to work on TRD/GEM
Nick active collimator
July 20
Scot, Josh, Chris walkthrough and HCO
Change out helium bottle regulator for gas analyzer
Sasha and Vlad to come in to add scintilator DS of PS - Sasha to indoctrinate Vlad
Sasha and Sergey B to install streaming readout - Sasha to accompany
Sasha to bring Josh Crafts in to sign paperwork
Replace Air Conditioner in BDX Tent - will buy anaother
Facilities (Mike Sprouse) Air Handling Unit Radcon swipe
Brian Eng - PXI calibration - No Joy
Beni to check Polarimeter signals w/scope
Lubomir to check analyzer
Chris Carlin - Target Controls computers
July21
Mark, Scot, Bobby, Chris walkthrough and HCO
BDX Fiber Optic Cable install
Facilities (Mike Sprouse) AHU maintenance 6:30am
Brian Eng Calibrate PXI
Sasha installing electronic modules
Mark Taylor Hall D training
Mark Taylor streaming readout ethernet cable
July 22
Mark, Josh, Keith walkthrough and HCO
Tim look at HCO and transfer on call phone
Look at adding shielding around tagger Turbos
Target HCO (Chris Keith morning)
Lubomir GEM/TRD
Sasha
Wednesday Lock up 3pm
July 23
Scot, Keith, Chris walkthrough and HCO
Clean Gas shed
Sasha and Josh Crafts measuring crystals
July 24
Mark, Josh, Bobby walkthrough and HCO
Lubomir and Condo GEM (Lubomir to brief Condo)
Sasha Electronics
Sergey DAQ
Eugene and Alexandre to get briefing
Nick AC bias
BDX Fiber cable install
July 25-26
Sasha coming in to work on crystals/ComCal
July 27
Scot, Keith and Chris walkthrough and HCO
Check out Lumi monitor cabling
Remove Lumi Monitor
Josh to set up welding certification tests in TEDF high bay
Sasha crystals in TEDF
July 28
Mark, Bobby and Keith walkthrough and HCO
Eugene to brief Simon, Elton, Mark I., Thomas and Keigo noonish
Josh and Chris welding certifications TEDF
Return Chiller to Solenoid PS
Hovanes Lumi check
Nick to check Lakeshores
Colin FCAL bases
Sasha crystals TEDF
July 29
Scot, Josh and Keith walkthrough and HCO
FCAL Vacuum pumpdown
Colin to check FCAL
Sasha ComCal crate check
Lubomir GEM
July 30
Mark, Bobby, Chris walkthrough
Complete all HCO - final check list first thing in morning
Bert safety HCO 8:30am
Tim final check
Colin FCAL
Alexandre 5pm to update run board
July 31
Scot, Josh, Keith walkthrough
Check to make sure the 1mm aluminum absorber is on profiler (access to Collimator cave needed)
Hall to controlled access Friday Noon - need someone there to help with the sweep
Eugene briefing for Alex, Igal etc..
Ramp Solenoid - Beni
Any more 4pm meetings?
Upcoming work
Tall plastic fence on US end of solenoid
Replace BDX chillers
References
List of referenced documents and their links
Hall D Resumption Plan File:Hall D Resumption Plan.pdf Hall D Resumption Schedule File:Hall D Resumption Schedule.pdf JLAB COVID-19 OSP File:JLAB COVID-19 OSP.pdf JLAB Web based Training https://www.jlab.org/human_resources/training/webbasedtraining Hall D Safety Page https://www.jlab.org/Hall-D/hd_safety.php Accelerator 8am meeting link https://jlab.bluejeans.com/569476853 Physics Medcon Operations Page https://physdiv.jlab.org/2020MedConOps/