Dec 16
From GlueXWiki
FCAl DAQ Plan
Triggers
- 1. Base pulser – electronics chain
- 2. Simple LED pulser – pmts whole
- 3. Cosmics – look for physics, self-trigger
- 4. Complete LED Monitoring System
Hardware Requirements:
- 1. NIM Bin (From ESB?)
- 2. Pulser (have)
- 3. NIM logic module
- 4. Discriminator
- 5. 12 CTPs
- 6. 2 SSPs
Tasks:
- 1. DAQ (trigger) configuration, CODA
- Done 12/5 - Alex
- 2. Readout pedestals, Generate analyzer to generate ROOT tree
- Alex, Sergey
- 3. Define working pedestals (JANA based), write scripts, produce list of pedestals
- Manuel, provided raw data and analyzer from Alex
- 4. Confirm electronics chain from ROOT files
- Pulse bases - IU
- 5. Confirm PMTs alive from ROOT files
- Simple LED setup - IU
- 6. Look for Cosmics from ROOT files
- Self-trigger - IU
- 7. Implement full LED pulsing system