Coil Test Weekly Meeting 29-Apr-2010

From GlueXWiki
Jump to: navigation, search

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 29-Apr-2010 9:30am ARC 428


Agenda

  • What controls equipment do we still need to buy (RS232? analog I/O? Dataforth modules?) - All
  • Controlling new valve - Elliott
  • Lehman review results - George
  • Wiring and testing controls racks - Scot, Mark S
    • Moving PLC from ARC 101 to F117 for testing
    • when do we need the hole in the wall?
  • Status of PLC programming - Mark W
    • Lakeshore calibrations
    • Additional RS232 and other devices
  • HMI and EWEB programming, UPS, terminal server, etc. - Yi, Elliott
    • Status of developing display pages and archiving
  • Safety review and progress towards getting OSP and COO - Elliott, Josh, Tim
    • OSP writing assignments and subject matter experts
    • P&I and wiring diagrams, machine protection diagrams, failure scenario analysis
  • EPICS connection to PLC - Elliott, Wesley
  • Installation progress - George
  • Coil 1 repair status - George
  • Coil 2 repair status - George
  • Coil 3 progress at IUCF - George
  • Coil 4 repair status - George