Coil Test Weekly Meeting 22-Jul-2010

From GlueXWiki
Jump to: navigation, search

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 22-Jul-2010 9:30am ARC 428


Agenda

  • Moving and F117 status - Scot, Mark S, Elliott
    • racks and computers
    • power
    • networking
    • telephone
  • Coil test plan - Josh
  • Magnet power supply and interlock commissioning - Cody
    • flow switches
    • insulation of dump resistor, interlocks, etc.
    • RS232 connection to power supply
    • lock door when magnet ramping down but power supply turned off?
    • interlock on strain gauges?
  • Controls racks - Scot
    • what else is left to do?
  • PLC programming/testing status - Mark W
    • what else is left to do besides testing?
  • UPS status - Mark W, Elliott
    • relay modules, use in interlock system
    • connection to PLC?
  • EPICS <--> PLC communications - Wesley, Elliott
    • connection to guard shack
  • HMI and EWEB programming - Yi, Elliott
  • Installation status - George, Mark S
    • rigging status
    • cryo can delivery
      • broken C-glass sensor in cryo can
    • Two weeks notice to Errol
    • backup power in Test Lab
  • Coil repair status - George
  • OSP documents and review - Elliott, George