Coil Test Weekly Meeting 14-Oct-2010
From GlueXWiki
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 14-Oct-2010 9:30 am ARC 428
Agenda
- Still more coil test group members, mainly in consultant/oversight capacity
- Bill Vulcan
- OSP docs and writing assignments - all
- Status
- Split into cryo and electrical
- What's left to do?
- Hall D Technical web page - Mark S
- Hall probe with fast readout for detection of turn-to-turn shorts- Mark S
- Pager for coil test on-call person - Elliott
- Installation status - all
- what's left?
- when do we give two weeks notice to Errol?
- Do we need He vessel LHe level in interlock system - George, Elliott
- backup to liquid level measurements?
- Magnet power supply and interlock commissioning - Mark S
- shunt
- ground fault detection
- Controls racks - Scot
- strain gauge interlock
- UPS interlock
- anything else?
- PLC programming/testing status - Mark W
- UPS interlock
- what's left?
- backup PLC programmer, file locations, license key
- EPICS <--> PLC communications - Hovanes
- connection to guard shack and notification conditions
- HMI and EWEB programming - Yi, Hovanes
- current status
- tutorial?
- Coil repair status - George
- Solenoid reviews 25-26 Oct and 7-Dec
- Purchase of another PLC and Ethernet module - Elliott
- Compatibility of other controls devices with PLC - Elliott
- Preparations for testing next coil - George, Scot, Elliott
- update P&I
- splices
- yoke location
- piping adaptors
- downstream yoke spacers
- controls racks rewiring
- connectors on next coil
- what else?