August 19, 2010 Des/Fab Meeting

From GlueXWiki
Jump to: navigation, search

Meeting Time and Place

Thursday Aug 19, 2010 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 428

Agenda

  • ESH&Q minute (Todd K.)
  • Announcements
  • Lehman review preparations *
  • Solenoid Test Status *
  • Manpower Estimates for 2011- 2014 *
  • Project Status *

Outstanding Action Items

  • Determine new positions of cryo transfer line supports and feedback to civil (Jim/Tim)* Under work - needs to be settled within the next few weeks
  • Correct platform height and location for new expansion can (make sure there is room to stab u-tubes)(Jim/Rich)* Some work done, will review next week
  • Need to develop a leak check and assy plan for cryo lines (Jim/Tom) in work
  • Consult with Scot and Mark on cryo instrumentation (Jim) in work - met with J. Creel from cryo - P&I diagrams given for review

Discussions

    • In attendance GW. Crahen, G. Biallas, T. Kujawa, J. Fochtman, T. Carstens, C. Hutton, V. Razmyslovich, J. Lagner, F. Martin, R. Getz, J. Foyles, M. Stevens, R. Bunton, G. Humble, C. Heck, D. Butler, K. Sullivan, Paul Collins, Tim Whitlatch
  • Todd presented a safety talk on multi-meter usage
  • Discussion on solenoid coil test preparation - Reliefs on bayonette can iare holding up work.
 Tinning of leads, platform installation (now grouted), ladder inst'l under way
 Cryo-connection designs still need some work, vacuum connections ready for review
 Power supply output contacts are miswired and are being addressed, cooling system now operational
  • Discussed manpower needs and upcoming work for 2011

Action Items

  • Look at getting traps/strainers for power supply LCW (Tom)
  • Identify PLC programmer to take over for Mark Wissman (Tim)
  • Need to put PR out for FDC techs (Tim)