Below are some general steps describing the trigger commissioning with the
 
Below are some general steps describing the trigger commissioning with the
photon beam. Note, commissioning may require significantly more time depending
+
photon beam.  
on the system performance.
+
  
 
=== Phase 1: Photon-beam Commissioning ===
 
=== Phase 1: Photon-beam Commissioning ===
Line 39: Line 38:
 
: - note, TAGM/TAGH could be read out using other trigger types
 
: - note, TAGM/TAGH could be read out using other trigger types
 
: - take data with TAGM/TAGH and the PS for the tagging efficiency study and calibration
 
: - take data with TAGM/TAGH and the PS for the tagging efficiency study and calibration
 +
 +
 +
Note, commissioning may require significantly more time depending
 +
on the system performance.

Revision as of 18:02, 14 September 2014

Below are some general steps describing the trigger commissioning with the photon beam.

Phase 1: Photon-beam Commissioning

  • PS stand alone trigger (2 - 3 days)
- trigger with PSC
- read out PS and PSC
- trigger distribution through GTP. Use PCS self trigger if problems with GTP

Phase 2: Photon Beam in the Hall

  • Tune FCAL trigger (2 - 3 days)
- trigger based on the global energy sum
- read out FCAL only, raw mode for fadc250
- adjust trigger parameters, tune timing
- study rates for various trigger thresholds
  • Add CDC, FDC, BCAL, ST, TOF (TAGM/TAGH) to the read out (4 - 5 days)
- tune timing, adjust trigger prescalings
  • Take some data for detector calibration
- production runs during nights if the system is robust
- run with high-energy thresholds
- low-energy thresholds for CDC/FDC calibration
  • Tune BCAL trigger (2 - 3 days)
- trigger based on the global energy sum
- alternate FCAL production runs with the BCAL trigger tuning
  • Production runs with BCAL (FCAL & BCAL) triggers
  • Tune TOF/ST triggers (4 - 5 days)
  • Take additional calibration data for CDC/FDC
  • Integrate & tune TAGM/TAGH to the trigger (low priority) (4 - 5 days)
- note, TAGM/TAGH could be read out using other trigger types
- take data with TAGM/TAGH and the PS for the tagging efficiency study and calibration


Note, commissioning may require significantly more time depending on the system performance.