Difference between revisions of "Trigger Commissioning"
From GlueXWiki
(→Phase 2: Photon Beam in the Hall) |
(→Phase 2: Photon Beam in the Hall) |
||
Line 11: | Line 11: | ||
* '''Tune FCAL trigger''' (2 - 3 days) | * '''Tune FCAL trigger''' (2 - 3 days) | ||
− | : - trigger | + | : - trigger based on the global energy sum |
: - read out FCAL only. Raw mode for fadc250 | : - read out FCAL only. Raw mode for fadc250 | ||
: - adjust trigger parameters, tune timing | : - adjust trigger parameters, tune timing |
Revision as of 17:48, 14 September 2014
Trigger Commissioning Plan
Phase 1: Photon-beam Commissioning
- PS stand alone trigger (2 - 3 days)
- - trigger with PSC
- - read out PS and PSC
- - trigger distribution through GTP. Use PCS self trigger if problems with GTP
Phase 2: Photon Beam in the Hall
- Tune FCAL trigger (2 - 3 days)
- - trigger based on the global energy sum
- - read out FCAL only. Raw mode for fadc250
- - adjust trigger parameters, tune timing
- - study rates for various trigger thresholds
- Add CDC, FDC, BCAL, ST, TOF (TAGM/TAGH) (4 - 5 days)
- - tune timing, adjust trigger prescalings
- Take some data for detector calibration
- - production runs during nights if the system is robust
- - run with high-energy thresholds
- - low-energy thresholds for CDC/FDC calibration
- Tune BCAL trigger (2 - 3 days)
- - trigger based on the global energy sum
- - alternate FCAL production runs with the BCAL trigger tuning
- Production runs with BCAL (FCAL & BCAL) triggers
- Tune TOF/ST triggers (4 - 5 days)
- Take additional calibration data for CDC/FDC
- Integrate & tune TAGM/TAGH to the trigger (low-priority) (4 - 5 days)
- - note, TAGM/TAGH could be read out using other trigger types
- - take data with TAGM/TAGH and the PS