Difference between revisions of "Trigger Commissioning"
From GlueXWiki
(→Phase 2: Photon Beam in the Hall) |
|||
Line 23: | Line 23: | ||
: - run with high-energy thresholds | : - run with high-energy thresholds | ||
: - low-energy thresholds for CDC/FDC calibration | : - low-energy thresholds for CDC/FDC calibration | ||
+ | |||
+ | * '''Tune BCAL trigger''' (2 - 3 days) | ||
+ | : - trigger based on the global energy sum | ||
+ | : - alternate |
Revision as of 17:37, 14 September 2014
Trigger Commissioning Plan
Phase 1: Photon-beam Commissioning
- PS stand alone trigger (2 - 3 days)
- - trigger with PSC
- - read out PS and PSC
- - trigger distribution through GTP. Use PCS self trigger if problems with GTP
Phase 2: Photon Beam in the Hall
- Tune FCAL trigger (2 - 3 days)
- - trigger using global energy
- - read out FCAL only. Raw mode for fadc250
- - adjust trigger parameters, tune timing
- - study rates for various trigger thresholds
- Add CDC, FDC, BCAL, ST, TOF (TAGM/TAGH) (4 - 5 days)
- - tune timing, adjust trigger prescalings
- Take some data for detector calibration
- - production runs during nights if the system is robust
- - run with high-energy thresholds
- - low-energy thresholds for CDC/FDC calibration
- Tune BCAL trigger (2 - 3 days)
- - trigger based on the global energy sum
- - alternate