Difference between revisions of "Trigger Commissioning"
From GlueXWiki
(→Phase 2: Photon Beam in the Hall) |
|||
Line 20: | Line 20: | ||
* '''Take some detector calibration data''' | * '''Take some detector calibration data''' | ||
− | : - production runs during nights ( | + | : - production runs during nights (if the system is robust) |
: - run with high-energy thresholds | : - run with high-energy thresholds | ||
: - low-energy thresholds for CDC/FDC calibration | : - low-energy thresholds for CDC/FDC calibration |
Revision as of 17:31, 14 September 2014
Trigger Commissioning Plan
Phase 1: Photon-beam Commissioning
- PS stand alone trigger (2 - 3 days)
- - trigger with PSC
- - read out PS and PSC
- - trigger distribution through GTP. Use PCS self trigger if problems with GTP
Phase 2: Photon Beam in the Hall
- Tune FCAL trigger (2 - 3 days)
- - trigger using global energy
- - read out FCAL only. Raw mode for fadc250
- - adjust trigger parameters, tune timing
- - study rates for various trigger thresholds
- Add CDC, FDC, BCAL, ST, TOF (TAGM/TAGH) (4 - 5 days)
- - tune timing, adjust trigger prescalings
- Take some detector calibration data
- - production runs during nights (if the system is robust)
- - run with high-energy thresholds
- - low-energy thresholds for CDC/FDC calibration