Difference between revisions of "Trigger Commissioning"

From GlueXWiki
Jump to: navigation, search
(Phase 2: Photon Beam in the Hall)
Line 20: Line 20:
  
 
* '''Take some detector calibration data'''  
 
* '''Take some detector calibration data'''  
: - production runs during nights (is the system is robust)
+
: - production runs during nights (if the system is robust)
 
: - run with high-energy thresholds
 
: - run with high-energy thresholds
 
: - low-energy thresholds for CDC/FDC calibration
 
: - low-energy thresholds for CDC/FDC calibration

Revision as of 17:31, 14 September 2014

Trigger Commissioning Plan

Phase 1: Photon-beam Commissioning

  • PS stand alone trigger (2 - 3 days)
- trigger with PSC
- read out PS and PSC
- trigger distribution through GTP. Use PCS self trigger if problems with GTP

Phase 2: Photon Beam in the Hall

  • Tune FCAL trigger (2 - 3 days)
- trigger using global energy
- read out FCAL only. Raw mode for fadc250
- adjust trigger parameters, tune timing
- study rates for various trigger thresholds
  • Add CDC, FDC, BCAL, ST, TOF (TAGM/TAGH) (4 - 5 days)
- tune timing, adjust trigger prescalings
  • Take some detector calibration data
- production runs during nights (if the system is robust)
- run with high-energy thresholds
- low-energy thresholds for CDC/FDC calibration