*'''Detector Electronics'''
 
*'''Detector Electronics'''
    ASIC (GAS-)
 
            V1 - Testing
 
            V2 - June 2009
 
    Preamp Card (GPC-)
 
            V1 - Testing
 
            V2 - July 2009
 
    Tagger (TAG)
 
      Analog Board
 
            V1 - Testing
 
            V2 - May 2009
 
      Digital Board
 
            V1 - Jan 2009
 
            V2 -
 
    Pair Spectrometer (PS)
 
    Start Counter (ST)
 
    Central Drift Chamber (CDC)
 
      HVB
 
            V1 - Complete
 
            V2 - Testing
 
    Forward Drift Chamber (FDC)
 
      HVTB
 
            V1 - Testing
 
            V2 -
 
      STB
 
            V1 - Testing
 
            V2 -
 
      Cathode Foils
 
            V1 - Sep 2008
 
            V2 -
 
      RigiFlex Signal
 
            V1 - Testing
 
            V2 - Jan 2009
 
      RigiFlex Ground
 
            V1 - Testing
 
            V2 - Jan 2009
 
    Barrel Calorimeter (BCAL)
 
      SiPM
 
            V1 - Dec 2008
 
            V2 -
 
    Time-of-Flight (TOF)
 
    Forward Calorimeter (FCAL)
 
      Cockcroft-Walton Multiplier
 
            V1 - Testing
 
            V2 -
 
  
* '''ADC & TDC Electronics - (Front-End)'''
+
* [https://halldweb.jlab.org/wiki/index.php/File:Rebaseline_Schedule.pdf Electronics installation schedule from March 2013 rebaseline]
    fADC125 - 125 MSPS flash ADC
+
            V1 - Mar 2009
+
            V2 -
+
    fADC250 - 250 MSPS flash ADC
+
            V1 - Testing
+
            V2 - Nov 2009
+
    F1TDC - 60/120 ps Multi-hit TDC
+
            V1 - Complete Oct 2002
+
            V2 - Sept 2009
+
 
+
* '''Trigger Electronics - (Back-End)'''
+
    Trigger Interface (TI)
+
            V1 - Testing (TI/TD)
+
            V2 -
+
    Signal Distribution (SD)
+
            V1 - Jan 2009
+
            V2 -
+
    Crate Trigger Processor (CTP)
+
            V1 - Jan 2009
+
            V2 -
+
    Sub-System Processor (SSP)
+
            V1 - May 2009
+
            V2 -
+
    Global Trigger Processor (GTP)
+
            V1 - Jul 2009
+
            V2 -
+
    Trigger Supervisor (TS)
+
            V1 - Jun 2009
+
            V2 -
+
    Trigger Distribution (TD)
+
            V1 - Apr 2009
+
            V2 -
+

Latest revision as of 05:48, 1 April 2015

Status & Schedules

  • Detector Electronics