==Status & Schedules==
 
==Status & Schedules==
  
* [[Detector Electronics]]
+
*'''Detector Electronics'''
    ASIC (GAS-)
+
            V1 - Testing
+
            V2 - June 2009
+
    Preamp Card (GPC-)
+
            V1 - Testing
+
            V2 - July 2009
+
    Tagger (TAG)
+
      Analog Board
+
            V1 - Testing
+
            V2 - May 2009
+
      Digital Board
+
            V1 - Jan 2009
+
            V2 -
+
    Pair Spectrometer (PS)
+
    Start Counter (ST)
+
    Central Drift Chamber (CDC)
+
      HVB
+
            V1 - Complete
+
            V2 - Testing
+
    Forward Drift Chamber (FDC)
+
      HVTB
+
            V1 - Testing
+
            V2 -
+
      STB
+
            V1 - Testing
+
            V2 -
+
      Cathode Foils
+
            V1 - Sep 2008
+
            V2 -
+
      RigiFlex Signal
+
            V1 - Testing
+
            V2 - Jan 2009
+
      RigiFlex Ground
+
            V1 - Testing
+
            V2 - Jan 2009
+
    Barrel Calorimeter (BCAL)
+
      SiPM
+
            V1 - Dec 2008
+
            V2 -
+
    Time-of-Flight (TOF)
+
    Forward Calorimeter (FCAL)
+
      Cockcroft-Walton Multiplier
+
            V1 - Testing
+
            V2 -
+
  
* [[ADC & TDC Electronics - (Front-End)]]
+
* [https://halldweb.jlab.org/wiki/index.php/File:Rebaseline_Schedule.pdf Electronics installation schedule from March 2013 rebaseline]
    fADC125 - 125 MSPS flash ADC
+
            V1 - Mar 2009
+
            V2 -
+
    fADC250 - 250 MSPS flash ADC
+
            V1 - Testing
+
            V2 - Nov 2009
+
    F1TDC - 60/120 ps Multi-hit TDC
+
            V1 - Complete Oct 2002
+
            V2 - Sept 2009
+
 
+
* [[Trigger Electronics - (Back-End)]]
+
    Trigger Interface (TI)
+
            V1 - Testing (TI/TD)
+
            V2 -
+
    Signal Distribution (SD)
+
            V1 - Jan 2009
+
            V2 -
+
    Crate Trigger Processor (CTP)
+
            V1 - Jan 2009
+
            V2 -
+
    Sub-System Processor (SSP)
+
            V1 - May 2009
+
            V2 -
+
    Global Trigger Processor (GTP)
+
            V1 - Jul 2009
+
            V2 -
+
    Trigger Supervisor (TS)
+
            V1 - Jun 2009
+
            V2 -
+
    Trigger Distribution (TD)
+
            V1 - Apr 2009
+
            V2 -
+