Solenoid Meeting 2014-02-04

From GlueXWiki
Revision as of 15:57, 10 February 2014 by Yqiang (Talk | contribs) (Created page with "== Attendees == George B., David B., Scot S., Yi Q. Eugene C. == Announcement == == Minutes == Review task list 47. PXI grounding: 90% done 52. Hall-prove location - between...")

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Attendees

George B., David B., Scot S., Yi Q. Eugene C.

Announcement

Minutes

Review task list

47. PXI grounding: 90% done

52. Hall-prove location - between 3 and 4, permanent, as close to center as possible. Discussion between Mark, Tom, Scot and Yi

3. LHe level probe, wiring issue - Scot

49. Coordinating system time - send PXI time to PLC - Yi

7. Sequence of Events (SOE) system done

8. More signals to SOE - refrigerator fault - firmware update - test/tweak code/ - David - in a week 85%

9. Ramp rate, front panel card fixed and installed, will test the power supply after installing the jumpers

10. Dump sequence - Giles talking to Dynfesik

11. Ground fault signal to PXI - Scot and Yi

51. Method to access old archive