Line 25: Line 25:
 
# FCAL
 
# FCAL
 
## Construction Status: mechanical, bases (notes from Matt)
 
## Construction Status: mechanical, bases (notes from Matt)
##* We received 10 first article COMM boards from Total Electronics. 
 
##* Assembly quality was not superb.  The main problem was that the solder was not heated enough (dull and gray instead of shiny).  Paul sent them back and we are waiting for a new batch.
 
 
# BCAL
 
# BCAL
 
## Construction Status: builds, fibre QA
 
## Construction Status: builds, fibre QA
 
# Simulations/Reconstruction
 
# Simulations/Reconstruction
 
# Beam tests in Hall B (fall 2011) (Kei)
 
# Beam tests in Hall B (fall 2011) (Kei)
 +
# Discussions of presentations at [[GlueX-Collaboration-Sep-2011]]
 
# Any other business
 
# Any other business
  
 
=Minutes=
 
=Minutes=
 
''Attending:
 
''Attending:

Revision as of 18:02, 7 September 2011

Teleconference Time: 11:00 a.m. EST'

  • ESNET (Number is 8542553) and EVO session (GlueX Calorimetry meeting room)
  • JLab Phone: in CC F326 is 757-269-6337; JLab Phone in CC L207 is 757-269-7084
  • Athens Phone: in Christina's office is 011-30-210-727-6947
  • Regina Phone: in LB228 is 306-585-4204
  • Phone connection only upon request.
    • +1-866-740-1260 : US+Canada
    • +1-303-248-0285 : International
    • then enter participant code: 3421244# (remember the "#").
    • or www.readytalk.com (and code without the #)

Items for followup from previous meeting(s)

  1. Monitoring
    • Athens and UofR needs for light guides from Chile and whether the new or old dimensions can be used. See e-mail from Zisis
  2. Beam test
    • Zisis will start a list of goals and requirements for the Bcal test.

Tentative Agenda

  1. Announcements
  2. Review of Action Items
  3. Monitoring
  4. FCAL
    1. Construction Status: mechanical, bases (notes from Matt)
  5. BCAL
    1. Construction Status: builds, fibre QA
  6. Simulations/Reconstruction
  7. Beam tests in Hall B (fall 2011) (Kei)
  8. Discussions of presentations at GlueX-Collaboration-Sep-2011
  9. Any other business

Minutes

Attending: