Difference between revisions of "Run Planning Meeting Notes, September 23 - September 29, 2021"

From GlueXWiki
Jump to: navigation, search
(Monday, September 27)
(Monday, September 27)
Line 9: Line 9:
 
#* Owl summary: https://logbooks.jlab.org/entry/3912249
 
#* Owl summary: https://logbooks.jlab.org/entry/3912249
 
#* Swing summary: https://logbooks.jlab.org/entry/3912060
 
#* Swing summary: https://logbooks.jlab.org/entry/3912060
#* Day summary:  
+
#* Friday am to Saturday 8am summary:
#* Check radiation level
+
#** FCAL HV scan
#* HARP scan
+
#** Beam back around 3 am
 +
#** Check radiation level
 +
#** HARP scan
 +
#* Saturday 8am to Sunday 8am summary:
 +
#** No beam from 10am to 8pm
 +
#** Beni & Richard debugged TAGM
 
# Issues
 
# Issues
 
#* TAGM wrongly cabling (Beni/Richard)
 
#* TAGM wrongly cabling (Beni/Richard)

Revision as of 14:02, 25 September 2021

<- Back to Run Coordination Meetings:Summer2021

Monday, September 27

  1. In last 72 hours:
  2. Issues
    • TAGM wrongly cabling (Beni/Richard)
    • Beam
  3. Plan

Friday, September 24

  1. In last 24 hours:
  2. Issues
  3. Plan
    • Compton with Be target at low intensity

Thursday, September 23

  1. In last 24 hours:
  2. Issues
  3. Plan for the day
    • tagm studies by Richard
    • FDC straight track studies by Lubomir