Difference between revisions of "Run Planning Meeting Notes, September 16 - September 23, 2021"
From GlueXWiki
(→Tuesday, September 16) |
|||
Line 6: | Line 6: | ||
#** Owl summary: https://logbooks.jlab.org/entry/3905917 | #** Owl summary: https://logbooks.jlab.org/entry/3905917 | ||
#** Early riser summary: https://logbooks.jlab.org/entry/3905955 | #** Early riser summary: https://logbooks.jlab.org/entry/3905955 | ||
− | #* Beam is being established to Hall D right now | + | #* Beam is being setup/established to Hall D right now |
#* CW and three Hall operations are expected at the end of the day shift. | #* CW and three Hall operations are expected at the end of the day shift. | ||
# Report/issue | # Report/issue |
Revision as of 08:20, 16 September 2021
<- Back to Run Coordination Meetings:Summer2021
Tuesday, September 16
- Last 24 hours:
- 5th Separator went well. Succifent Separatoion achieved.
- Shift started at 10 pm last night.
- Owl summary: https://logbooks.jlab.org/entry/3905917
- Early riser summary: https://logbooks.jlab.org/entry/3905955
- Beam is being setup/established to Hall D right now
- CW and three Hall operations are expected at the end of the day shift.
- Report/issue
- Remote shifter feedback on Blue Jeans connection: sound is intermittent. Currently, not workable. https://logbooks.jlab.org/entry/3905912
- TAGM scaler reset: https://logbooks.jlab.org/entry/3905724
- News on hydra
- Run plan
- Wait for beam delivery. Begin experiment commissioning. Run plan