Thursday, September 15

Past 24 Hours

Issues

Plan

  • Take production data at 200nA with Full target
  • Trigger rate scan today ???

Friday, September 16

Past 24 Hours

Issues

Plan

  • Continue taking production data at 200nA with Full target

Saturday, September 17

Past 24 hours

  • Production data at 200nA on the liquid He target.
    • ~3.5B total triggers collected last 24 hours
  • Beam was OFF for ~1pm to 18:10pm, during the down time works been done in hall
    • Sergey replaced some RF modules in FDC
    • Malte fixed 2 FCAL bases
    • Konda worked on GEM-TRD

Issues

Plan

  • Continue taking production data at 200nA on LHe.

Sunday, September 18

Past 24 hours

  • Production data at 200nA on the liquid He target.
    • ???B total triggers collected last 24 hours
  • Beam was OFF for ~12:00pm to 22:30
  • Then from ~05:30 till about 12:00pm
  • After beam is back harp scan was performed
    • RF HPA (transformer) broken

Issues

  • No major issues in the Hall
  • Some Fcal channels were alarming (contacted to Malte)
  • RF issues from ACC site

Plan

  • Continue taking production data at 200nA on LHe.


Monday, September 19

Past 24 hours

  • Production data at 200nA on the liquid He target.
  • Beam was OFF for ~5:30am to 12:00pm
  • After beam is back harp scan was performed

Issues

  • No major issues in the Hall
  • Some Fcal channels were alarming
  • Daq crashed once over the weekend
  • Sergey and Sasha changed Daq configuration to high luminosity mode

Plan

  • Switch to Empty Target, production data at 200nA.
  • There have been a couple of beam extended down time over the weekend (overall>24hours), will decide today should we move to empty target
  • from 7:45 meeting -> probably there will be RF recovery on Tuesday during ACC entire day shift
  • Solenoid Relief Membrane work (Tuesday), need to ramp dawn magnet to ~800A

Tuesday, September 20

Past 24 hours

  • Production data at 200nA on EMPTY target.
  • Switched to Empty Target 10:00am (Sep-19)
  • Beam was not stable, couple extended down times
  • After beam is back harp scan was performed (12:50pm)

Issues

  • No major issues in the Hall
  • around 4:50 the AC was acted very slow when beam was back (Beni)


Plan

  • RF Recovery Day (Day shift)
  • Switch back to Full LHe Target, production data at 200nA.
  • After hall is surveyed at ~8:30ish, stay in Controlled access
  • Solenoid Relief Membrane work (Tuesday), need to ramp dawn magnet to ~800A (Tim)
  • Work on FCAL bases (Malte)
  • Check AC status (Beni)
  • Work on GEM-TRD (Kondo)

Friendly REMINDER to all groups and persons working in the hall during the access, Make a log entry what was DONE, PLEASE