=== Past 24 hours === | === Past 24 hours === | ||
* Data collection resumed at 4:19 am with TOF issue | * Data collection resumed at 4:19 am with TOF issue | ||
+ | * [https://logbooks.jlab.org/entry/4052776 Beam transmission after long beam down time] | ||
* [https://logbooks.jlab.org/entry/4052675 HARP scan] | * [https://logbooks.jlab.org/entry/4052675 HARP scan] | ||
* Beam back at 3:30 am | * Beam back at 3:30 am |
Revision as of 09:05, 9 October 2022
Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Back to Run Coordination Meetings:Fall2022
Contents
Sunday, October 9
Past 24 hours
- Data collection resumed at 4:19 am with TOF issue
- Beam transmission after long beam down time
- HARP scan
- Beam back at 3:30 am
- Target FULL & Ready at 6:45 pm
- LCW 2 reached at 5 pm on Saturday
- Shift summary
Issues
Plan
Thursday, October 6
Past 24 hours
Issues
- MCC still trying to fix magnets
Plan
- Production data on helium target