Difference between revisions of "Run Planning Meeting Notes, October 21 - October 27, 2021"
From GlueXWiki
(→Friday, October 22) |
|||
Line 1: | Line 1: | ||
<-- [https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:Summer2021 Summer 2021 RC meetings] [https://cebaf.jlab.org/files/ops/accboard/ MCC whiteboard] | <-- [https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:Summer2021 Summer 2021 RC meetings] [https://cebaf.jlab.org/files/ops/accboard/ MCC whiteboard] | ||
+ | |||
+ | =Happenings since the Friday morning meeting= | ||
+ | #* No news from the accelerator yet but everyone seemed optimistic at the morning meeting. | ||
+ | #* Started filling the target a little before 9:30, with Chris Keith watching, and the shift crew here. | ||
+ | #* We went into controlled access so that Tim could go in to do something for CPP. | ||
+ | |||
+ | =Friday, October 22= | ||
+ | # Last 24h: Production runs continued smoothly until 2:51pm when an arc magnet tripped. About 7pm the team looking at the power supply found that there was a short in any one of the 42 magnets downstream, they will resume work in the morning. [https://logbooks.jlab.org/entry/3930057 Shifts were cancelled until 9am.] | ||
+ | {| border="0" cellpadding="2" | ||
+ | |[[Image:arc7.png|thumb|x300px|arc 7 trip]] | ||
+ | |} | ||
+ | #* [https://logbooks.jlab.org/entry/3929614 extra PS shielding added on Wednesday] | ||
+ | #* [https://logbooks.jlab.org/entry/3929964 FCAL comms restored] | ||
+ | #* [https://logbooks.jlab.org/entry/3928806 Alarm added on tagger magnet current] | ||
+ | # Remaining issues: | ||
+ | #* BCAL noise at 10 o'clock | ||
+ | #* Bleedthrough | ||
+ | # [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:] | ||
+ | #* Call Chris Keith (to watch the target fill). | ||
+ | #* When the beam is back, continue production at 200nA after the usual checks (radiation levels & harp scans) | ||
+ | #* Continue running with the solenoid on & target full until further notice | ||
+ | #* [https://cebaf.jlab.org/files/ops/accboard/ Pass change for A&B might be deferred to Saturday swing or Sunday day (A->4 pass)] | ||
+ | #* Expect downtime Monday morning for VIP tour, start time TBC probably ~7am. | ||
=Thursday, October 21= | =Thursday, October 21= | ||
Line 23: | Line 46: | ||
#* Expect downtime Monday morning for VIP tour, start time TBC probably ~7am. | #* Expect downtime Monday morning for VIP tour, start time TBC probably ~7am. | ||
#* Ops will need another maintenance day before the energy change | #* Ops will need another maintenance day before the energy change | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− |
Revision as of 09:52, 22 October 2021
<-- Summer 2021 RC meetings MCC whiteboard
Happenings since the Friday morning meeting
- No news from the accelerator yet but everyone seemed optimistic at the morning meeting.
- Started filling the target a little before 9:30, with Chris Keith watching, and the shift crew here.
- We went into controlled access so that Tim could go in to do something for CPP.
Friday, October 22
- Last 24h: Production runs continued smoothly until 2:51pm when an arc magnet tripped. About 7pm the team looking at the power supply found that there was a short in any one of the 42 magnets downstream, they will resume work in the morning. Shifts were cancelled until 9am.
- Remaining issues:
- BCAL noise at 10 o'clock
- Bleedthrough
- Plan:
- Call Chris Keith (to watch the target fill).
- When the beam is back, continue production at 200nA after the usual checks (radiation levels & harp scans)
- Continue running with the solenoid on & target full until further notice
- Pass change for A&B might be deferred to Saturday swing or Sunday day (A->4 pass)
- Expect downtime Monday morning for VIP tour, start time TBC probably ~7am.
Thursday, October 21
- Last 24h:
- No beam from 5:20pm Tuesday until early am Thurs due to LCW/power problem. Resumed production ~3:30am.
- New harp scan Previous harp scan
- Work done during the access:
- magnetic field measurements around CCAL
- 15 FCAL bases replaced and re-terminated one cable
- faulty FDC chiller replaced
- rebalanced the server power load on rack 13
- position survey CCAL
- correct shielding at the left (downstream) PS arm
- Remaining issues:
- Tagger hodoscope time shifts
- communication with accel. w.r.t. tagger magnet - Paul Vasilauskis (Ops group leader): "I am putting out to my staff to contact the hall if they do need to touch the magnet and am looking into adding wording to the magnet screens"
- BCAL noise at 10 o'clock
- Bleedthrough
- Plan:
- When the beam is back continue production at 200nA after the usual checks (radiation levels & harp scans)
- Continue running with the solenoid on & target full until Friday or later
- Pass change for A&B Saturday morning (A->4 pass)
- Expect downtime Monday morning for VIP tour, start time TBC probably ~7am.
- Ops will need another maintenance day before the energy change