Difference between revisions of "Run Planning Meeting Notes, Oct 4-Oct 10, 2018"

From GlueXWiki
Jump to: navigation, search
Line 22: Line 22:
 
#** 0930 access
 
#** 0930 access
 
#***TAC run preparation, Hovanes with ARM to install the Pb converter
 
#***TAC run preparation, Hovanes with ARM to install the Pb converter
#***Parallel (rapid) access for Beni (CDC) and Tim (PS)
+
#***Parallel (rapid) access for Beni (CDC) and Tim (PS). Others?
 
#***Radcon repair to radiation monitor to fix the alarm in counting room  
 
#***Radcon repair to radiation monitor to fix the alarm in counting room  
 
#** Hovanes will calibrate A.C. high gain setting (am, after access)
 
#** Hovanes will calibrate A.C. high gain setting (am, after access)

Revision as of 23:52, 3 October 2018

<- Back to Run Coordination Meetings:Fall2018 Run

Wednesday, Oct 3 at 08:45

  1. Notes from the previous 24 hours:
  2. CEBAF:
  3. Action Items:
  4. Issues:
  5. Reports:
    • Monitoring
  6. Run Plan:
    • Week 2 Week 3 Week 4
    • Thursday
      • 0930 access
        • TAC run preparation, Hovanes with ARM to install the Pb converter
        • Parallel (rapid) access for Beni (CDC) and Tim (PS). Others?
        • Radcon repair to radiation monitor to fix the alarm in counting room
      • Hovanes will calibrate A.C. high gain setting (am, after access)
    • Friday
      • TAC run
        • Hall C will be down from 7am for 6-8h
        • MCC need ~2h to set up low current, ETA 0830-0900, setup DAQ (~1h, Sasha), take data for 4-5h. (Go to 30nA & V-wire if we run out of Hall C downtime).
    • Weekend and longer term
      • High rate tests of L1 trigger and DAQ
      • Rate comparison test
      • RF Recovery on Tuesday, who needs an access?
    • Acc whiteboard
    • Counting house whiteboard
  7. AOB