Difference between revisions of "Run Planning Meeting Notes, Oct 4-Oct 10, 2018"

From GlueXWiki
Jump to: navigation, search
(Created page with "<- Back to Run Coordination Meetings:Fall2018 Run <!-- * [https://halldweb.jlab.org/data_monitoring/run_statistics/RunPeriod-2018-01/index.html Trigger graphs] Comment -...")
 
Line 8: Line 8:
 
== Wednesday, Oct 3 at 08:45 ==
 
== Wednesday, Oct 3 at 08:45 ==
 
# Notes from the previous 24 hours:
 
# Notes from the previous 24 hours:
#* Sasha completed PS trigger studies
+
#* Note
#* 6 hopefully good production runs
+
#* Lost beam for half of swing w He fault in accelerator; less stable during owl & then off for 2h for cryo module failure
+
#* Length of run -> 300M & 150M (<2h for calibrations, daq is running much better than previously, full cycle of 5 runs takes too long)
+
 
#CEBAF:
 
#CEBAF:
 
#Action Items:
 
#Action Items:
#* Microscope occupancy is off - should be fixed when Richard has loaded new thresholds
+
#* Microscope occupancy is still unreliable - should be fixed when Richard has loaded new thresholds
 
#Issues:  
 
#Issues:  
#* Few daq issues - ending runs, and rate dropped towards end of day shift
+
#* placeholder
#* Goniometer camera stuck in owl, ok after restarting gui
+
#*[https://logbooks.jlab.org/entry/3602980 Rates on diamond are decreasing (Alexandre)]
+
 
# Reports:
 
# Reports:
 
#*Monitoring  
 
#*Monitoring  
Line 32: Line 27:
 
#*[https://halldweb.jlab.org/online/whiteboard/ Counting house whiteboard]
 
#*[https://halldweb.jlab.org/online/whiteboard/ Counting house whiteboard]
 
# AOB
 
# AOB
#*Next RC: Stuart Fegan
 
#*(Offline note for Stuart: add Curtis's spreadsheet to the RC notes for the meeting tomorrow)
 

Revision as of 16:14, 3 October 2018

<- Back to Run Coordination Meetings:Fall2018 Run

Wednesday, Oct 3 at 08:45

  1. Notes from the previous 24 hours:
    • Note
  2. CEBAF:
  3. Action Items:
    • Microscope occupancy is still unreliable - should be fixed when Richard has loaded new thresholds
  4. Issues:
    • placeholder
  5. Reports:
    • Monitoring
  6. Run Plan:
    • Week 2 Week 3 Week 4
    • TAC run prep on Thursday
      • 0930 Quick access for Hovanes with ARM to install the Pb converter; also remember to call Melvin from radcon to fix the alarm (number on whiteboard & alarm)
      • Hovanes will calibrate A.C. high gain setting on Thurs am.
    • TAC run on Friday
      • Hall C will be down from 7am for 6-8h
      • MCC need ~2h to set up low current, ETA 0830-0900, setup DAQ (~1h, Sasha), take data for 4-5h. (Go to 30nA & V-wire if we run out of single-hall time).
    • Acc whiteboard
    • Counting house whiteboard
  7. AOB