Difference between revisions of "Run Planning Meeting Notes, November 24 - November 30, 2022"

From GlueXWiki
Jump to: navigation, search
(Drama)
(Issues)
Line 27: Line 27:
  
 
=== Issues ===
 
=== Issues ===
 +
* Monday 1am - many problems: DAQ errors from several crates, then CCAL HV unit. Sergey was called in.
 
* The top alcohol bubbler is approaching the Add line.
 
* The top alcohol bubbler is approaching the Add line.
 
* [https://logbooks.jlab.org/entry/4090024 One Ar cylinder is empty]
 
* [https://logbooks.jlab.org/entry/4090024 One Ar cylinder is empty]
 
* [https://logbooks.jlab.org/entry/4090130 Reconstructed Beam Energy monitoring plot discrepancy in recent runs] (Drew)
 
* [https://logbooks.jlab.org/entry/4090130 Reconstructed Beam Energy monitoring plot discrepancy in recent runs] (Drew)
 
* No beam for ~2h Saturday with [https://logbooks.jlab.org/entry/4091621 vacuum issue], ~1h with [https://logbooks.jlab.org/entry/4091908 trips] in swing shift. Also see the drama section.
 
* No beam for ~2h Saturday with [https://logbooks.jlab.org/entry/4091621 vacuum issue], ~1h with [https://logbooks.jlab.org/entry/4091908 trips] in swing shift. Also see the drama section.
* The CH kitchen light switches off automatically but does not switch on automatically, is it supposed to?
+
* The CH kitchen light switches off automatically but does not switch on automatically, is it supposed to? Better to switch it off on exit.
 
+
  
 
=== Shift Summaries ===
 
=== Shift Summaries ===

Revision as of 04:20, 28 November 2022

Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Hall D Logbook

Back to Run Coordination Meetings:Fall2022

Monday Nov 28

The plan

Achievements

  • Production running with full target, 10.3B triggers as of Saturday 10pm
  • Filled the target on Wednesday morning after approximately 2B triggers with empty target.
  • Raw mode cosmics run 111571 (Beni)
  • FCAL base changed (Malte)
  • Several locked up FCAL bases reset Wed early riser Wed day Fri early riser

Drama

  • Wednesday pm - cooling water outage summary and more stripcharts. We lost about 2h beam-time time fixing problems and waiting for the target to refill; it was another 2h before the BCAL chiller temps returned to normal.

Issues