(Thursday, Nov 8 at 08:45)
(Thursday, Nov 8 at 08:45)
Line 13: Line 13:
 
#Last 24h:
 
#Last 24h:
 
#* TAC run with empty target, v-wire at 50nA, reduced field in PS (400A), low E TAGH counters on
 
#* TAC run with empty target, v-wire at 50nA, reduced field in PS (400A), low E TAGH counters on
 +
#** [https://logbooks.jlab.org/entry/3622665 logbook entry with preliminary analysis]
 
#* Beam tuning
 
#* Beam tuning
 
#* Data taking with reduced PS field, coherent edge at 7GeV
 
#* Data taking with reduced PS field, coherent edge at 7GeV

Revision as of 18:44, 7 November 2018

<- Back to Run Coordination Meetings:Fall2018 Run

Thursday, Nov 8 at 08:45

  1. Last 24h:
    • TAC run with empty target, v-wire at 50nA, reduced field in PS (400A), low E TAGH counters on
    • Beam tuning
    • Data taking with reduced PS field, coherent edge at 7GeV
  2. Issues
    • PS and PSC coincidence scalers frozen, ps_client running on gluon100 restarted, instructions in hdops wiki
    • beam position went awry, rates soared, reference module for IOC reading out 5C11B failed, replaced
    • EPICS froze for 2h, started working without intervention
  3. Reports
    • Monitoring
  4. Plans
  5. Notes