  Work on Injector to reduce the trips, work ongoing during day shift(how long?),HI test  Pb and Mo foils, Production? ABU=? hr
+
  Work on Injector,HI test  Pb and Mo foils, Production? ABU=? hr
  
 
=== Shift Reports ===
 
=== Shift Reports ===

Revision as of 11:39, 8 March 2023

Zoom Connect Meeting ID: 160 199 0060 / Passcode 8394

MCC Whiteboard

Hall D counting room white board

Spreadsheet with list of runs

Integrated Trigger Count

Hall D Logbook



Thursday March 9

Past 24 hours

Work on Injector,HI test  Pb and Mo foils, Production? ABU=? hr

Shift Reports

  • [ Early Riser Shift Summary]
  • Day Shift Summary
  • [ Swing Shift Summary]
  • [ Owl Shift Summary]

Reports

Issues

Plans

  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)