= Friday, March 15 2024=
 +
=== Past 24 hours ===
 +
* Smooth running. Many rapid accesses for transition radiator configuration changes.
 +
 +
* Shift Summary
 +
** [https://logbooks.jlab.org/entry/4266611 Day Monday]
 +
** [https://logbooks.jlab.org/entry/4266779 Swing Monday]
 +
** [https://logbooks.jlab.org/entry/4266904 Owl Tuesday]
 +
 +
 +
* ABUs: 7.7 h
 +
<!-- * Data Summary:  B triggers on empty target -->
 +
 +
=== Issues ===
 +
*
 +
 +
=== Report ===
 +
*[https://logbooks.jlab.org/entry/4266711 Radiator comparison (Lubomir)]
 +
 +
=== Plan ===
 +
* Data taking with Kr until beam termination later today (around swing shift?)
 +
* Hall B believe they will work until Friday mid-afternoon. Hall D beam is expected to be turned off at about that time.
 +
* Link to runplan: https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:Winter2024#Runplan
 +
 +
= Wednesday, March 13 2024=
 +
=== Past 24 hours ===
 +
* Yesterday was efficient (15.5h ABU)
 +
** Photon beam was established and test of the GEM-TRD and GEM started.
 +
** Rapid-access between noon and 14:00 to look at GEM-TRD and GEM.
 +
** Beam back only at 16:40 due to Hall D magnet ramp issue.
 +
** 20:05-20:25 [https://logbooks.jlab.org/entry/4265803 Tagger magnet trip/restoration]
 +
 +
* Shift Summary
 +
** [https://logbooks.jlab.org/entry/4265482 Day Monday]
 +
** [https://logbooks.jlab.org/entry/4265738 Swing Monday]
 +
** [https://logbooks.jlab.org/entry/4265876 Owl Tuesday]
 +
 +
 +
* ABUs: 15.5 h
 +
<!-- * Data Summary:  B triggers on empty target -->
 +
 
= Thursday, March 14 2024=
 
= Thursday, March 14 2024=
 
=== Past 24 hours ===
 
=== Past 24 hours ===

Revision as of 06:39, 15 March 2024

Friday, March 15 2024

Past 24 hours

  • Smooth running. Many rapid accesses for transition radiator configuration changes.


  • ABUs: 7.7 h

Issues

Report

Plan

Wednesday, March 13 2024

Past 24 hours

  • Yesterday was efficient (15.5h ABU)
    • Photon beam was established and test of the GEM-TRD and GEM started.
    • Rapid-access between noon and 14:00 to look at GEM-TRD and GEM.
    • Beam back only at 16:40 due to Hall D magnet ramp issue.
    • 20:05-20:25 Tagger magnet trip/restoration


  • ABUs: 15.5 h

Thursday, March 14 2024

Past 24 hours


  • ABUs: 7.7 h

Issues

Report

Plan

Wednesday, March 13 2024

Past 24 hours

  • Yesterday was efficient (15.5h ABU)
    • Photon beam was established and test of the GEM-TRD and GEM started.
    • Rapid-access between noon and 14:00 to look at GEM-TRD and GEM.
    • Beam back only at 16:40 due to Hall D magnet ramp issue.
    • 20:05-20:25 Tagger magnet trip/restoration


  • ABUs: 15.5 h

Issues

  • Amo radiator/harp motor. (Access today to investigate it)


Questions

  • Man shifts for Friday swing?

Plan

Tuesday, March 12 2024

Past 24 hours

  • 6:37 LCW fluctuation tripped PS magnet.
  • Hall C pass change completed early afternoon. Then, Ops started to tune hall D beam.
  • 17:30 Ops starting to tune beam to Hall D tagger.
  • 23:30 Although the first amorphous radiator motion was normal, it got stuck in its way to get retracted.
    • Hovanes reduced motor speed to 30% of nominal
    • We decided to drop the program on 10-4 and 3×10-4 RL radiators, as well as Ion Chambers threshold calib. on those. We also drop the plan for our Harp scan since it uses the same motor.
  • 01:05 radiator motion issue again despite reduced speed
  • 03:20 Ion Chamber calibration done (2×10-5 radiator only because of motor issue)
  • 05:20 Active Collimator calibration done (high gain only because of radiator motor issue)
  • Transmission looks decent: 5kHz rate in the PSC counters compared to expected 8.7kHz for optimal, converging, beam (100 nA, 2×10-5 RL 750um TPOL converter)



  • ABUs: 0 h

Issues


Questions

    • Access to tagger today or Wednesday to look at amorphous radiator/harp motor?
    • Man shifts for Friday day/swing?

Plan