(Tuesday, March 12 2024)
(Tuesday, March 12 2024)
Line 7: Line 7:
 
** Hovanes reduced motor speed to 30% of nominal
 
** Hovanes reduced motor speed to 30% of nominal
 
** We decided to drop the program on 10<sup>-4</sup> and 3*10<sup>-4</sup> RL radiators, as well as Ion Chambers threshold calib. on those. We also drop the plan for our Harp scan since it uses the same motor.  
 
** We decided to drop the program on 10<sup>-4</sup> and 3*10<sup>-4</sup> RL radiators, as well as Ion Chambers threshold calib. on those. We also drop the plan for our Harp scan since it uses the same motor.  
 +
* 01:05 [https://logbooks.jlab.org/entry/4265328 radiator motion issue again despite reduced speed]
 +
* 03:20 Ion Chamber calibration done (2*10<sup>-5</sup> radiator only because of motor issue)
 +
* 05:20 Active Colimator calibration done (high gain only because of radiator motor issue)
  
* To-do
+
*MCC Harp scans: [https://logbooks.jlab.org/entry/4265217 5C00], [https://logbooks.jlab.org/entry/4265288 5C11], [https://logbooks.jlab.org/entry/4265289 5C11b]
**Noon: rapid access (2h, 5 persons) for DAQ and detector work.
+
 
+
*Questions:
+
**Access to tagger to look at amorphous radiator/harp motor?
+
**Man shifts for Friday day/swing?
+
 
+
  
  
Line 27: Line 24:
  
 
=== Issues ===
 
=== Issues ===
*
+
* Amo radiator/harp motor.
 +
* [https://logbooks.jlab.org/entry/4265319 Notable bleedthrough] (unexpected but not an issue?). It is clearly correlated with beam on in Hall C. [https://logbooks.jlab.org/entry/4265328 It seems it was fixed during the night]
 +
 
 +
 
 +
*Questions:
 +
**Access to tagger to look at amorphous radiator/harp motor?
 +
**Man shifts for Friday day/swing?
 +
 
 +
 
 +
 
 
=== Plan ===
 
=== Plan ===
 
* Noon: rapid access (2h, 5 persons) for DAQ and detector work.   
 
* Noon: rapid access (2h, 5 persons) for DAQ and detector work.   
 
* Link to runplan: https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:Winter2024#Runplan
 
* Link to runplan: https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:Winter2024#Runplan

Revision as of 07:34, 12 March 2024

Tuesday, March 12 2024

Past 24 hours

  • 6:37 LCW fluctuation tripped PS magnet.
  • Hall C pass change completed early afternoon. Then, Ops started to tune hall D beam.
  • 17:30 Ops starting to tune beam to Hall D tagger.
  • 23:30 Although the first amorphous radiator motion was normal, it got stuck in its way to get retracted.
    • Hovanes reduced motor speed to 30% of nominal
    • We decided to drop the program on 10-4 and 3*10-4 RL radiators, as well as Ion Chambers threshold calib. on those. We also drop the plan for our Harp scan since it uses the same motor.
  • 01:05 radiator motion issue again despite reduced speed
  • 03:20 Ion Chamber calibration done (2*10-5 radiator only because of motor issue)
  • 05:20 Active Colimator calibration done (high gain only because of radiator motor issue)



  • ABUs: h

Issues


  • Questions:
    • Access to tagger to look at amorphous radiator/harp motor?
    • Man shifts for Friday day/swing?


Plan