Difference between revisions of "Run Planning Meeting Notes, Mar 29-Apr 4, 2018"

From GlueXWiki
Jump to: navigation, search
(Thursday, March 28 at 08:45)
(Thursday, March 28 at 08:45)
Line 5: Line 5:
 
#* RF separator tested out ok, aimed to restore beam for swing shift but delayed due to CHL issues  
 
#* RF separator tested out ok, aimed to restore beam for swing shift but delayed due to CHL issues  
 
#* Beam arrived just before midnight, convergence not good, owl shift spent tuning
 
#* Beam arrived just before midnight, convergence not good, owl shift spent tuning
#* 0800 MCC meeting notes - Todd retuning; planning machine work 4h Mon, 8h Tues
+
#* 0800 MCC meeting notes - Todd retuning; planning machine work 4h Mon, 8h Tues [https://cebaf.jlab.org/files/ops/accboard/ MCC whiteboard]
 
#Issues:
 
#Issues:
 
#* Shift-takers should at least log any acknowledged alarms so that they are not forgotten
 
#* Shift-takers should at least log any acknowledged alarms so that they are not forgotten
Line 18: Line 18:
 
#* SSP Study (Alex S.)
 
#* SSP Study (Alex S.)
 
#* Production running
 
#* Production running
 +
# AOB
 +
 +
== Friday, March 29 at 08:45 ==
 +
# Notes from the previous 24 hours:
 +
#* 0800 MCC meeting notes
 +
#** [https://cebaf.jlab.org/files/ops/accboard/ MCC whiteboard]
 +
#Issues:
 +
# Reports:
 +
# Run Plan [https://halldweb.jlab.org/wiki/index.php/File:Spring18_week12.jpg Schematic]
 
# AOB
 
# AOB

Revision as of 09:19, 29 March 2018

<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run

Thursday, March 28 at 08:45

  1. Notes from the previous 24 hours:
    • RF separator tested out ok, aimed to restore beam for swing shift but delayed due to CHL issues
    • Beam arrived just before midnight, convergence not good, owl shift spent tuning
    • 0800 MCC meeting notes - Todd retuning; planning machine work 4h Mon, 8h Tues MCC whiteboard
  2. Issues:
    • Shift-takers should at least log any acknowledged alarms so that they are not forgotten
    • Is there a how-to page for the BTA sheet? (load from epics, edit etc & guidelines on ABU/BANU)
  3. Reports:
  4. Run Plan
    • Re-establish Photon beam
    • 1h production to check beam quality & detectors
    • Diamond spot adjustment (Hovanes)
    • CDC Background Studies (Lubomir et al.)
    • Converter thickness study (Alex S.)
    • SSP Study (Alex S.)
    • Production running
  5. AOB

Friday, March 29 at 08:45

  1. Notes from the previous 24 hours:
  2. Issues:
  3. Reports:
  4. Run Plan Schematic
  5. AOB