Difference between revisions of "Run Planning Meeting Notes, February 9 - February 15, 2023"
From GlueXWiki
(→Past 24 hours) |
(→Past 24 hours) |
||
Line 14: | Line 14: | ||
=== Past 24 hours === | === Past 24 hours === | ||
− | * | + | * Beam back at 11:25 pm |
+ | ** Shift crew forgot to change the collimator from blocking to 5 mm and start moving the collimator while the beam was on | ||
* HARP scans | * HARP scans | ||
** [https://logbooks.jlab.org/entry/4126952 HarpFitter:IHA5C11] | ** [https://logbooks.jlab.org/entry/4126952 HarpFitter:IHA5C11] | ||
Line 20: | Line 21: | ||
** [https://logbooks.jlab.org/entry/4126976 Scan result for HALO:T:gamma:tag:top:scaler_r1_vs_ hd:radiator:motor.RBV] | ** [https://logbooks.jlab.org/entry/4126976 Scan result for HALO:T:gamma:tag:top:scaler_r1_vs_ hd:radiator:motor.RBV] | ||
** [https://logbooks.jlab.org/entry/4126985 Results] | ** [https://logbooks.jlab.org/entry/4126985 Results] | ||
+ | * No beam from 10 am to 10:30 pm | ||
=== Shift Reports === | === Shift Reports === |
Revision as of 00:28, 9 February 2023
Zoom connect Meeting ID: 160 199 0060 / Passcode 8394
Hall D counting room white board
Contents
Wednesday February 9
Past 24 hours
- Beam back at 11:25 pm
- Shift crew forgot to change the collimator from blocking to 5 mm and start moving the collimator while the beam was on
- HARP scans
- No beam from 10 am to 10:30 pm
Shift Reports
Reports
- Statistics balance
- PARA 0/90: 19%
- PERP 0/90: 19%
- PARA 45/135: 21%
- PERP 45/135: 18%
- AMO : 24%
Issues
Pending:
- Start Counter (Beni) - We do not understand why there is a mismatch in the software between start counter and tracking.
- BCM calibration. Alexandre recommends that we request a recalibration of AD00C BCM.
Plans
- Production (300 nA, 2h runs) with cycle:
- 2 runs PARA (0/90)
- 2 runs PERP (0/90)
- 2 runs PARA (45/135)
- 2 runs PERP (45/135)
- 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)