Line 4: | Line 4: | ||
* [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1635471172 Trigger Spreadsheet] | * [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1635471172 Trigger Spreadsheet] | ||
* [https://calendar.google.com/calendar/embed?src=halldops%40gmail.com&src=503o985nbesua43smquc510o8k%40group.calendar.google.com&ctz=America/New_York Google Calendar] | * [https://calendar.google.com/calendar/embed?src=halldops%40gmail.com&src=503o985nbesua43smquc510o8k%40group.calendar.google.com&ctz=America/New_York Google Calendar] | ||
+ | |||
+ | |||
+ | == Monday, February 11 == | ||
+ | # Notes from the previous 24 hours: | ||
+ | #* No beam since Friday | ||
+ | # Issues: | ||
+ | #* [https://logbooks.jlab.org/entry/3530267 Quad MQPAD00 value] | ||
+ | # Today's run plan [https://calendar.google.com/calendar/embed?src=halldops%40gmail.com&src=503o985nbesua43smquc510o8k%40group.calendar.google.com&ctz=America/New_York Google Calendar]: | ||
+ | #* Production | ||
+ | # Reports (?): | ||
+ | # Standing issues: | ||
+ | |||
+ | |||
+ | |||
+ | |||
== Friday, February 8 == | == Friday, February 8 == |
Revision as of 09:25, 12 February 2018
<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run
Monday, February 11
- Notes from the previous 24 hours:
- No beam since Friday
- Issues:
- Today's run plan Google Calendar:
- Production
- Reports (?):
- Standing issues:
Friday, February 8
- Notes from the previous 24 hours:
- Rapid Access Approved! Collimator cave excluded.
- FCAL signal testing Two broken lemo connectors at the base, two unplugged lemo cables, one swapped base
- Trigger rates available in epics
- Harp scans show good convergence
- Difficulty starting DAQ (reboot rocPS1)
- Low level monitoring
- Muon chamber light leak fix
- Issues:
- Today's run plan Google Calendar:
- PROGRAM INTERRUPTION
- Shifts on standby (until Saturday Swing? pending further information from MCC)
- PROGRAM INTERRUPTION
- Reports (?):
- Standing issues:
- Weekend meeting?
Thursday, February 8
- Notes from the previous 24 hours:
- 30 minutes of raw mode data
- 4 hours Low intensity running with min bias trigger trigger rate
- TAGM columns fixed during opportunistic access, board swap, parameters changed
- TAGH time and time with respect to the main trigger OK
- Harp scans show good convergence
- Low level monitoring
- surpassed 40 billion triggers
- Issues:
- What goal/expectation should we express to MCC?
- Today's run plan Google Calendar:
- Beam will be taken to steer the injector to make A and C beams colinear
- Opportunistic access for FCAL bases and to retrieve microscope preamp
- Beam will be taken to steer the injector to make A and C beams colinear
- Reports (?):
- Initial TPOL results are available. More work needed, ~3% statistical uncertainties, poor chi2
- Rate evolution
- Standing issues: